SpendingContractsPurchase order

What has the City paid on purchase order SC50MSACO14123672KO?

$6.97M paid to 2 different vendors (the largest, Ohl USA Inc, received $4.3M) across 9 payments from July 11, 2017 to September 19, 2018, charged to Non-Departmental / Machado Lake Ecosystem Rehab.

A blanket order, not one firm's contract

2 different vendors draw against this purchase order, so the $7.0M above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

What it was for

Machado Lake Ecosystem Rehab

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Gob 2011A Clean Water Cleanup

a capital fund, typically bond or grant financed rather than annual tax revenue.

Department: Non-Departmental

Paid to

Ohl USA Inc$4.3M · 3 payments
Ohl-USA Inc$2.7M · 6 payments

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1July 11, 2017June 20, 201721dMACHADO LAKE ECOSYSTEM REHABILITATION$350,884
2July 25, 2017June 19, 201736dMACHADO LAKE ECOSYSTEM REHABILITATION$56,250
3July 25, 2017June 2, 201753dMACHADO LAKE ECOSYSTEM REHABILITATION$19,269
4August 14, 2017August 9, 20175dMACHADO LAKE ECOSYSTEM REHAB,CHANGE ORDERS#043=$16,994.00$82,344
5August 25, 2017August 16, 20179dMACHADO LAKE ECOSYSTEM REHAB,CHANGE ORDERS#043=$16,994.00$186,848
6September 11, 2017August 30, 201712dMACHADO LAKE ECOSYSTEM REHAB,PP#41, EW40022F$2,000,040
7December 26, 2017December 8, 201718dMACHADO LAKE ECOSYSTEM REHAB,CHANGE ORDERS#045=$52,467.00$1,125,980
8January 17, 2018January 12, 20185dSN RELEASE-AMERICAN LANDSCAPE/MACHADO LAKE ECOSYSTEM REHAB,C#123672$751,458
9September 19, 2018August 30, 201820dMACHADO LAKE ECOSYSTEM REHABILITATION.-ENCUMBER,CH.ORD#46=$2,200,000.00$2,400,143