SpendingContractsPurchase order

What has the City paid on purchase order SC50CO25144945K?

$6.38M paid to Jilk Heavy Construction Inc. across 33 payments from September 9, 2024 to March 18, 2026, charged to Non-Departmental / Kinney Street Improvements Project.

What it was for

Kinney Street Improvements Project

Budget line carrying the most money, of 7 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Road Maintenance and Rehabilitation Program Special Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1September 9, 2024July 23, 202448dNTP 1 & NTP_REV E1909215 BENEDICT CANYON DR 59V/50YZBR$408,416
2October 2, 2024September 25, 20247dNTP 1 E1908943 MEDINA RD 59V/50WVIK$559,966
3October 17, 2024October 9, 20248dNTP 1 & NTP_REV E1909215 BENEDICT CANYON DR 59V/50YZBR$19,338
4November 25, 2024November 14, 202411dNTP 1 E1908943 MEDINA RD 59V/50WVIK$173,331
5December 26, 2024December 19, 20247dNTP 1 E1908943 MEDINA RD 59V/50WVIK$310,896
6January 17, 2025January 8, 20259dNTP 1 & NTP 1 REV E1908478 KINNEY ST 59V/50VVGM$498,463
7January 17, 2025January 8, 20259dNTP 1 REV E1908478 KINNEY ST 59V/50RKHS$474,895
8January 22, 2025January 8, 202514dNTP 1 & NTP_REV E1909215 BENEDICT CANYON DR 59V/50YZBR$79,234
9February 12, 2025February 3, 20259dNTP 1 E1908943 MEDINA RD 59V/50WVIK$118,138
10February 26, 2025February 14, 202512dNTP 1 & NTP 1 REV E1908478 KINNEY ST 59V/50VVGM$298,137
11February 26, 2025February 14, 202512dNTP 1 REV E1908478 KINNEY ST 59V/50WVII$106,035
12March 4, 2025February 20, 202512dNTP 1 E1909196 CRSCENT DR 59V/50AZCD$108,067
13March 19, 2025March 5, 202514dE1908943 MEDINA RD 59V/50WVIK NTP & CO$130,486
14March 27, 2025March 18, 20259dNTP 1 E1909196 CRSCENT DR 59V/50AZCD$130,852
15March 28, 2025March 21, 20257dNTP 1 REV E1908478 KINNEY ST 59V/50WVII$54,759
16April 25, 2025April 10, 202515dNTP 1 E1909196 CRSCENT DR 59V/50AZCD$5,664
17May 12, 2025April 28, 202514dNTP 1 REV E1908478 KINNEY ST 59V/50WVII$461,780
18May 15, 2025May 1, 202514dE1908943 MEDINA RD 59V/50WVIK NTP & CO$36,491
19May 22, 2025May 12, 202510dNTP 1 E1909196 CRESCENT DR 59V/50AZCD$12,048
20July 9, 2025June 26, 202513dE1908943 MEDINA RD 59V/50WVIK NTP & CO$66,016
21July 28, 2025July 18, 202510d59V/50/50YVII/E1908478/KINNEY/CO#1, 2$252,334
22July 28, 2025July 18, 202510dNTP 1 REV E1908478 KINNEY ST 59V/50WVII$235,425
23July 29, 2025July 21, 20258dE1909252/59V/50/50AZCE/NTP 1 (REVISED) DTD 6/4/25 ENCHANTED$306,712
24July 29, 2025July 21, 20258d59V/50/50YVII/E1908478/KINNEY/CO#1, 2$15,967
25August 13, 2025July 28, 202516dNTP + FCCO E1909196 CRESCENT DR 59V/50AZCD$16,794
26August 18, 2025August 7, 202511dE1909252/59V/50/50AZCE/NTP 1 (REVISED) DTD 6/4/25 ENCHANTED$242,640
27September 15, 2025September 5, 202510d59V/50/50YVII/E1908478/KINNEY/CO#1, 2$165,876
28September 17, 2025September 10, 20257dE1909252/59V/50/50AZCE/NTP 1 (REVISED) DTD 6/4/25 ENCHANTED$207,479
29September 22, 2025September 12, 202510dE1908943 MEDINA RD 59V/50WVIK NTP & CO$67,073
30October 22, 2025October 16, 20256d59V/50/50YVII/E1908478/KINNEY/CO#1, 2$319,300
31December 1, 2025November 12, 202519dE1909252/59V/50/50AZCE/NTP 1 (REVISED) DTD 6/4/25 ENCHANTED$229,563
32February 13, 2026February 10, 20263dE1909252/59V/50/50AZCE/NTP 1 (REVISED) DTD 6/4/25 ENCHANTED$48,442
33March 18, 2026March 3, 202615d59V/50/50YVII/E1908478/KINNEY/COS$223,449

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.