SpendingContractsPurchase order
What has the City paid on purchase order SC50CO24144220M?
$1.95M paid to G2 Construction Inc. across 14 payments from August 5, 2024 to August 27, 2026, charged to Non-Departmental / Operation and Maintenance - TMDL Compliance Projects.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Measure W - Safe, Clean Water - Municipal Program SF
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Non-Departmental
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | August 5, 2024 | February 26, 2024 | 161d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $45,600 |
| 2 | August 9, 2024 | August 9, 2024 | 0d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $27,751 |
| 3 | August 9, 2024 | August 9, 2024 | 0d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $15,134 |
| 4 | August 12, 2024 | August 6, 2024 | 6d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $445,063 |
| 5 | August 12, 2024 | August 9, 2024 | 3d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $247,719 |
| 6 | October 17, 2024 | May 13, 2024 | 157d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $12,378 |
| 7 | December 10, 2024 | September 24, 2024 | 77d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $10,122 |
| 8 | March 11, 2025 | November 12, 2024 | 119d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $25,561 |
| 9 | March 12, 2025 | November 8, 2024 | 124d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $343,685 |
| 10 | December 10, 2025 | September 24, 2025 | 77d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $457,634 |
| 11 | December 12, 2025 | October 2, 2025 | 71d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $29,213 |
| 12 | May 21, 2026 | April 27, 2026 | 24d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $15,829 |
| 13 | August 3, 2026 | April 27, 2026 | 98d | FABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS | $1,358 |
| 14 | August 27, 2026 | June 16, 2026 | 72d | CB BMP REPLACEMENT PROJECT | $272,508 |