SpendingContractsPurchase order

What has the City paid on purchase order SC50CO24144220M?

$1.95M paid to G2 Construction Inc. across 14 payments from August 5, 2024 to August 27, 2026, charged to Non-Departmental / Operation and Maintenance - TMDL Compliance Projects.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Measure W - Safe, Clean Water - Municipal Program SF

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 5, 2024February 26, 2024161dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$45,600
2August 9, 2024August 9, 20240dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$27,751
3August 9, 2024August 9, 20240dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$15,134
4August 12, 2024August 6, 20246dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$445,063
5August 12, 2024August 9, 20243dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$247,719
6October 17, 2024May 13, 2024157dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$12,378
7December 10, 2024September 24, 202477dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$10,122
8March 11, 2025November 12, 2024119dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$25,561
9March 12, 2025November 8, 2024124dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$343,685
10December 10, 2025September 24, 202577dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$457,634
11December 12, 2025October 2, 202571dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$29,213
12May 21, 2026April 27, 202624dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$15,829
13August 3, 2026April 27, 202698dFABRICATION AND INSTALLATION OF FULL CAPTURE CATCH BASIN INSERTS AND CURB OPENING SCREEN COVERS$1,358
14August 27, 2026June 16, 202672dCB BMP REPLACEMENT PROJECT$272,508