SpendingContractsPurchase order

What has the City paid on purchase order SC50CO24144066K?

$24.86M paid to Los Angeles Engineering, Inc. across 120 payments from December 19, 2023 to August 21, 2026, charged to Non-Departmental / Six Landscaping Elements.

What it was for

Six Landscaping Elements

Budget line carrying the most money, of 11 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

MICLA Lease Rev Com Paper Ntes

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1December 19, 2023November 20, 202329dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$2,211,551
2December 19, 2023November 20, 202329dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$609,868
3December 19, 2023November 20, 202329dF298/50MSTF WO#E700235F-SIXTH STREET VIADUCT-PARC$190,000
4December 19, 2023November 20, 202329dF298/50RSIX WO#E700235F-SIXTH STREET VIADUCT-PARC$161,169
5January 17, 2024December 8, 202340dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$1,923,642
6January 17, 2024December 8, 202340dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$32,782
7February 8, 2024January 25, 202414dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$208,069
8February 27, 2024February 9, 202418dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$944,740
9February 27, 2024February 9, 202418dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$710,556
10April 30, 2024April 23, 20247dC144066-15 CO#5DISENCUMBER $33,723 CO#5 WO#E700235F-SIXTH STREET VIADUCT-PARC$266,215
11April 30, 2024April 23, 20247dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$184,444
12April 30, 2024March 11, 202450dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$146,062
13May 7, 2024April 8, 202429d682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$31,488
14May 8, 2024April 8, 202430dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$120,207
15May 22, 2024May 2, 202420dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$230,883
16May 23, 2024May 2, 202421dF298/50RLDS WO#E700235F-SIXTH STREET VIADUCT-PARC$734,389
17May 23, 2024May 2, 2013—F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$130,198
18June 7, 2024May 24, 202414dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$96,095
19June 14, 2024May 24, 202421dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$819,595
20June 14, 2024May 24, 202421dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$471,822
21June 14, 2024May 24, 202421dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$200,000
22July 17, 2024July 1, 202416dF298/50VLDS WO#E700235F-SIXTH STREET VIADUCT-PARC$1,000,000
23July 17, 2024July 1, 202416dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$152,324
24July 17, 2024July 1, 202416dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$96,156
25July 17, 2024July 1, 202416dF298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC$42,782
26July 19, 2024July 1, 202418dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$71,182
27August 21, 2024August 1, 202420dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$743,006
28August 21, 2024August 1, 202420dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$499,228
29August 21, 2024August 1, 202420dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$47,936
30August 21, 2024August 1, 202420dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$32,208
31October 2, 2024September 19, 202413dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$1,136,804
32October 2, 2024September 19, 202413dF298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC$539,145
33October 2, 2024September 19, 202413dINCREASE ENCUMBRANCE 50RLDS $74,397 FOR CO #'S 16 & 18$63,642
34October 23, 2024October 1, 202422dINCREASE ENCUMBRANCE 50RLDS $122,210 FOR CO #'S 7, 15, 17, 23 & 26$116,100
35October 23, 2024October 1, 202422dINC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC$14,318
36December 6, 2024November 4, 202432dINCREASE ENCUMBRANCE 50RLDS $1,060,045.15 FOR CO #'S 19, 20 & 30$373,680
37December 6, 2024November 4, 202432dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$254,989
38January 7, 2025December 6, 202432dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$164,319
39January 7, 2025December 6, 202432dINCREASE ENCUMBRANCE 50RLDS $36,398.57 FOR CO #'S 24 & 31$96,673
40January 7, 2025December 6, 202432dADD ENCUMBRANCE 50RLDS $36,398.57 FOR CO #'S 24 & 31$36,399
41January 15, 2025December 6, 202440dPMT#14, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$5,520
42January 16, 2025December 6, 202441dPMT#14, SZC14224$104,878
43January 23, 2025December 31, 202423dPMT#15, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$1,154
44January 27, 2025December 31, 202427dPMT#15, SZC14224$21,921
45February 25, 2025February 11, 202514dPMT#16, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$200
46February 27, 2025February 11, 202516dPMT#16, SZC14224$3,800
47March 10, 2025February 11, 202527dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$1,525,160
48March 10, 2025February 11, 202527dINC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35$105,826
49March 11, 2025March 3, 20258dPMT#17, ESCROW #2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$747
50March 13, 2025March 3, 202510dPMT#17, SZC14224$14,194
51April 10, 2025March 27, 202514dADD CL13, AL1 ENCUMBER 298/50RLDS $157,987 FOR CHANGE ORDER #'S 8, 25, 29, 38, 42, 44, 46-48$138,916
52April 10, 2025March 27, 202514dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$89,720
53April 10, 2025March 27, 202514dINC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35$10,348
54April 15, 2025March 28, 202518dPMT#18, ESCROW# 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$888
55April 17, 2025March 28, 202520dPMT#18, SZC14224$16,865
56April 24, 2025April 15, 20259dINC ENC CL13, AL1 ENCUMBER 298/50RLDS $840,586 FOR CHANGE ORDER #'S 3, 40, 41, 43, 49, 50, 56&57$479,475
57May 9, 2025March 28, 202542dENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$100,671
58May 21, 2025May 2, 202519dPMT#19, ESCROW # 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$100
59May 23, 2025May 2, 202521dPMT#19, SZC14224$1,898
60June 2, 2025May 2, 202531dENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$343,197
61June 9, 2025May 23, 202517dPMT#20, ESCROW# 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$100
62June 11, 2025June 3, 20258dINC ENC CL13, AL1 ENCUMBER 298/50RLDS $479,295 FOR CHANGE ORDER #'S 52 & 58$634,690
63June 11, 2025June 2, 20259dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$2,318
64June 11, 2025May 23, 202519dPMT#20, SZC14224$1,895
65June 20, 2025May 23, 202528dINC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61$106,305
66June 20, 2025May 23, 202528dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$80,017
67June 20, 2025May 23, 202528dINC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35$50,582
68August 11, 2025July 9, 202533dPMT#21, SZC14224$1,895
69August 11, 2025July 9, 202533dPMT#21, OVERCHARGED RETENTION FOR ITEM#32 IN PR#14 AND #18 -PARTIAL $99.76 OUT OF $1,000.00,SZC14224$100
70August 12, 2025July 9, 202534dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$7,118
71August 20, 2025August 4, 202516dPMT#22, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$1,399
72August 27, 2025August 4, 202523dPMT#22, SZC14224$43,684
73August 27, 2025August 4, 202523dPMT#22, OVERCHARGED RETN FOR ITEM#32 IN PR#14 AND 18 - REMAINING PART $900.24 OUT OF $1,000,SZC14224$900
74September 3, 2025August 4, 202530dINC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35$70,815
75September 3, 2025August 4, 202530dINC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61$2,093
76September 22, 2025September 4, 202518dPMT#23, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$248
77September 24, 2025September 4, 202520dPMT#23, SZC14224$4,717
78November 4, 2025October 2, 202533dPMT#24, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$100
79November 5, 2025September 4, 202562dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$146,707
80November 5, 2025September 4, 202562dINC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35$60,699
81November 5, 2025September 4, 202562dINC ENC CL14, AL1 ENCUMBER 298/50RLDS $27,410.35 FOR CO#65$27,410
82November 5, 2025September 4, 202562dINC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61$1,395
83November 6, 2025October 2, 202535dPMT#24, SZC14224$1,895
84November 10, 2025September 4, 202567dENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$1,170,624
85November 12, 2025October 2, 202541dENC. 682/50LVBC $750,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$500,000
86November 12, 2025October 2, 202541dENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$316,865
87November 12, 2025September 4, 202569dENC. 682/50LVBC $750,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$250,000
88November 12, 2025October 2, 202541dINC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35$202,329
89November 12, 2025October 2, 202541dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$178,404
90November 12, 2025October 2, 202541dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$111,348
91November 19, 2025November 5, 202514dPMT#25, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$100
92November 24, 2025November 5, 202519dPMT#25, SZC14224$17,895
93November 25, 2025November 5, 202520dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$30,506
94December 12, 2025November 5, 202537dINC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC$457,165
95December 12, 2025November 5, 202537dINC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61$2,994
96December 23, 2025December 5, 202518dPMT#26, ESCROW NO. 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$1,885
97December 30, 2025December 5, 202525dPMT#26, SZC14224$19,817
98January 21, 2026December 5, 202547dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$88,977
99January 26, 2026December 31, 202526dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$204,393
100January 26, 2026December 31, 202526dPMT#27, SZC14224$66,212
101January 26, 2026December 31, 202526dPMT#27, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$3,485
102March 10, 2026February 6, 202632dPMT#28, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$10,888
103March 11, 2026February 6, 202633dPMT#28, SZC14224$206,867
104April 17, 2026April 1, 202616dPMT#30, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224$1,602
105April 21, 2026April 1, 202620dPMT#30, SZC14224$30,440
106April 29, 2026April 15, 202614dPMT#30, WO#E700235F, SIXTH ST VIADUCT-PARC 2/27/26-3/31/26, C144066$53,520
107May 11, 2026April 1, 202640dENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT$106,948
108May 21, 2026May 4, 202617dPMT#31, SZC14224$61,845
109May 21, 2026May 4, 202617dPMT#31, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$3,255
110June 11, 2026June 9, 20262dPMT#31, CO#8, WO#E700235F, SIXTH ST VIADUCT-PARC 4/1/26-4/30/26, C144066$50,582
111June 11, 2026June 9, 20262dPMT#31, CO#8, WO#E700235F, SIXTH ST VIADUCT-PARC 4/1/26-4/30/26, C144066$998
112June 17, 2026May 22, 202626dPMT#32, SZC14224$312,703
113June 17, 2026May 22, 202626dPMT#32, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, SZC14224$15,452
114June 17, 2026May 22, 202626dPMT#32, SZC14224$890
115July 8, 2026June 16, 202622dPMT#32, CO#19, WO#E700235F, SIXTH ST VIADUCT-PARC$101,165
116July 8, 2026June 16, 202622dPMT#32, CO#8, WO#E700235F, SIXTH ST VIADUCT-PARC$998
117July 28, 2026July 8, 202620dPMT#33, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224$444
118July 29, 2026July 8, 202621dPMT#33, SZC14224$8,436
119August 21, 2026August 3, 202618dPMT#34, WO#E700235F, SIXTH ST VIADUCT-PARC, 7/1/26-7/30/26, C144066$145,922
120August 21, 2026August 3, 202618dPMT#34, CO#54, WO#E700235F, SIXTH ST VIADUCT-PARC 7/1/26-7/30/26, C144066$3,313

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.