What has the City paid on purchase order SC50CO24144066K?
$24.86M paid to Los Angeles Engineering, Inc. across 120 payments from December 19, 2023 to August 21, 2026, charged to Non-Departmental / Six Landscaping Elements.
What it was for
Six Landscaping ElementsBudget line carrying the most money, of 11 this order is charged to.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
MICLA Lease Rev Com Paper Ntes
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Non-Departmental
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | December 19, 2023 | November 20, 2023 | 29d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $2,211,551 |
| 2 | December 19, 2023 | November 20, 2023 | 29d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $609,868 |
| 3 | December 19, 2023 | November 20, 2023 | 29d | F298/50MSTF WO#E700235F-SIXTH STREET VIADUCT-PARC | $190,000 |
| 4 | December 19, 2023 | November 20, 2023 | 29d | F298/50RSIX WO#E700235F-SIXTH STREET VIADUCT-PARC | $161,169 |
| 5 | January 17, 2024 | December 8, 2023 | 40d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $1,923,642 |
| 6 | January 17, 2024 | December 8, 2023 | 40d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $32,782 |
| 7 | February 8, 2024 | January 25, 2024 | 14d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $208,069 |
| 8 | February 27, 2024 | February 9, 2024 | 18d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $944,740 |
| 9 | February 27, 2024 | February 9, 2024 | 18d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $710,556 |
| 10 | April 30, 2024 | April 23, 2024 | 7d | C144066-15 CO#5DISENCUMBER $33,723 CO#5 WO#E700235F-SIXTH STREET VIADUCT-PARC | $266,215 |
| 11 | April 30, 2024 | April 23, 2024 | 7d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $184,444 |
| 12 | April 30, 2024 | March 11, 2024 | 50d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $146,062 |
| 13 | May 7, 2024 | April 8, 2024 | 29d | 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $31,488 |
| 14 | May 8, 2024 | April 8, 2024 | 30d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $120,207 |
| 15 | May 22, 2024 | May 2, 2024 | 20d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $230,883 |
| 16 | May 23, 2024 | May 2, 2024 | 21d | F298/50RLDS WO#E700235F-SIXTH STREET VIADUCT-PARC | $734,389 |
| 17 | May 23, 2024 | May 2, 2013 | — | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $130,198 |
| 18 | June 7, 2024 | May 24, 2024 | 14d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $96,095 |
| 19 | June 14, 2024 | May 24, 2024 | 21d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $819,595 |
| 20 | June 14, 2024 | May 24, 2024 | 21d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $471,822 |
| 21 | June 14, 2024 | May 24, 2024 | 21d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $200,000 |
| 22 | July 17, 2024 | July 1, 2024 | 16d | F298/50VLDS WO#E700235F-SIXTH STREET VIADUCT-PARC | $1,000,000 |
| 23 | July 17, 2024 | July 1, 2024 | 16d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $152,324 |
| 24 | July 17, 2024 | July 1, 2024 | 16d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $96,156 |
| 25 | July 17, 2024 | July 1, 2024 | 16d | F298/50RCSR WO#E700235F-SIXTH STREET VIADUCT-PARC | $42,782 |
| 26 | July 19, 2024 | July 1, 2024 | 18d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $71,182 |
| 27 | August 21, 2024 | August 1, 2024 | 20d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $743,006 |
| 28 | August 21, 2024 | August 1, 2024 | 20d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $499,228 |
| 29 | August 21, 2024 | August 1, 2024 | 20d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $47,936 |
| 30 | August 21, 2024 | August 1, 2024 | 20d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $32,208 |
| 31 | October 2, 2024 | September 19, 2024 | 13d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $1,136,804 |
| 32 | October 2, 2024 | September 19, 2024 | 13d | F298/50MCON WO#E700235F-SIXTH STREET VIADUCT-PARC | $539,145 |
| 33 | October 2, 2024 | September 19, 2024 | 13d | INCREASE ENCUMBRANCE 50RLDS $74,397 FOR CO #'S 16 & 18 | $63,642 |
| 34 | October 23, 2024 | October 1, 2024 | 22d | INCREASE ENCUMBRANCE 50RLDS $122,210 FOR CO #'S 7, 15, 17, 23 & 26 | $116,100 |
| 35 | October 23, 2024 | October 1, 2024 | 22d | INC ENCR $119,606 CO#4,9-13 WO#E700235F-SIXTH STREET VIADUCT-PARC | $14,318 |
| 36 | December 6, 2024 | November 4, 2024 | 32d | INCREASE ENCUMBRANCE 50RLDS $1,060,045.15 FOR CO #'S 19, 20 & 30 | $373,680 |
| 37 | December 6, 2024 | November 4, 2024 | 32d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $254,989 |
| 38 | January 7, 2025 | December 6, 2024 | 32d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $164,319 |
| 39 | January 7, 2025 | December 6, 2024 | 32d | INCREASE ENCUMBRANCE 50RLDS $36,398.57 FOR CO #'S 24 & 31 | $96,673 |
| 40 | January 7, 2025 | December 6, 2024 | 32d | ADD ENCUMBRANCE 50RLDS $36,398.57 FOR CO #'S 24 & 31 | $36,399 |
| 41 | January 15, 2025 | December 6, 2024 | 40d | PMT#14, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $5,520 |
| 42 | January 16, 2025 | December 6, 2024 | 41d | PMT#14, SZC14224 | $104,878 |
| 43 | January 23, 2025 | December 31, 2024 | 23d | PMT#15, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $1,154 |
| 44 | January 27, 2025 | December 31, 2024 | 27d | PMT#15, SZC14224 | $21,921 |
| 45 | February 25, 2025 | February 11, 2025 | 14d | PMT#16, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $200 |
| 46 | February 27, 2025 | February 11, 2025 | 16d | PMT#16, SZC14224 | $3,800 |
| 47 | March 10, 2025 | February 11, 2025 | 27d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $1,525,160 |
| 48 | March 10, 2025 | February 11, 2025 | 27d | INC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35 | $105,826 |
| 49 | March 11, 2025 | March 3, 2025 | 8d | PMT#17, ESCROW #2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $747 |
| 50 | March 13, 2025 | March 3, 2025 | 10d | PMT#17, SZC14224 | $14,194 |
| 51 | April 10, 2025 | March 27, 2025 | 14d | ADD CL13, AL1 ENCUMBER 298/50RLDS $157,987 FOR CHANGE ORDER #'S 8, 25, 29, 38, 42, 44, 46-48 | $138,916 |
| 52 | April 10, 2025 | March 27, 2025 | 14d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $89,720 |
| 53 | April 10, 2025 | March 27, 2025 | 14d | INC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35 | $10,348 |
| 54 | April 15, 2025 | March 28, 2025 | 18d | PMT#18, ESCROW# 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $888 |
| 55 | April 17, 2025 | March 28, 2025 | 20d | PMT#18, SZC14224 | $16,865 |
| 56 | April 24, 2025 | April 15, 2025 | 9d | INC ENC CL13, AL1 ENCUMBER 298/50RLDS $840,586 FOR CHANGE ORDER #'S 3, 40, 41, 43, 49, 50, 56&57 | $479,475 |
| 57 | May 9, 2025 | March 28, 2025 | 42d | ENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $100,671 |
| 58 | May 21, 2025 | May 2, 2025 | 19d | PMT#19, ESCROW # 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $100 |
| 59 | May 23, 2025 | May 2, 2025 | 21d | PMT#19, SZC14224 | $1,898 |
| 60 | June 2, 2025 | May 2, 2025 | 31d | ENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $343,197 |
| 61 | June 9, 2025 | May 23, 2025 | 17d | PMT#20, ESCROW# 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $100 |
| 62 | June 11, 2025 | June 3, 2025 | 8d | INC ENC CL13, AL1 ENCUMBER 298/50RLDS $479,295 FOR CHANGE ORDER #'S 52 & 58 | $634,690 |
| 63 | June 11, 2025 | June 2, 2025 | 9d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $2,318 |
| 64 | June 11, 2025 | May 23, 2025 | 19d | PMT#20, SZC14224 | $1,895 |
| 65 | June 20, 2025 | May 23, 2025 | 28d | INC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61 | $106,305 |
| 66 | June 20, 2025 | May 23, 2025 | 28d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $80,017 |
| 67 | June 20, 2025 | May 23, 2025 | 28d | INC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35 | $50,582 |
| 68 | August 11, 2025 | July 9, 2025 | 33d | PMT#21, SZC14224 | $1,895 |
| 69 | August 11, 2025 | July 9, 2025 | 33d | PMT#21, OVERCHARGED RETENTION FOR ITEM#32 IN PR#14 AND #18 -PARTIAL $99.76 OUT OF $1,000.00,SZC14224 | $100 |
| 70 | August 12, 2025 | July 9, 2025 | 34d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $7,118 |
| 71 | August 20, 2025 | August 4, 2025 | 16d | PMT#22, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $1,399 |
| 72 | August 27, 2025 | August 4, 2025 | 23d | PMT#22, SZC14224 | $43,684 |
| 73 | August 27, 2025 | August 4, 2025 | 23d | PMT#22, OVERCHARGED RETN FOR ITEM#32 IN PR#14 AND 18 - REMAINING PART $900.24 OUT OF $1,000,SZC14224 | $900 |
| 74 | September 3, 2025 | August 4, 2025 | 30d | INC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35 | $70,815 |
| 75 | September 3, 2025 | August 4, 2025 | 30d | INC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61 | $2,093 |
| 76 | September 22, 2025 | September 4, 2025 | 18d | PMT#23, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $248 |
| 77 | September 24, 2025 | September 4, 2025 | 20d | PMT#23, SZC14224 | $4,717 |
| 78 | November 4, 2025 | October 2, 2025 | 33d | PMT#24, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $100 |
| 79 | November 5, 2025 | September 4, 2025 | 62d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $146,707 |
| 80 | November 5, 2025 | September 4, 2025 | 62d | INC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35 | $60,699 |
| 81 | November 5, 2025 | September 4, 2025 | 62d | INC ENC CL14, AL1 ENCUMBER 298/50RLDS $27,410.35 FOR CO#65 | $27,410 |
| 82 | November 5, 2025 | September 4, 2025 | 62d | INC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61 | $1,395 |
| 83 | November 6, 2025 | October 2, 2025 | 35d | PMT#24, SZC14224 | $1,895 |
| 84 | November 10, 2025 | September 4, 2025 | 67d | ENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $1,170,624 |
| 85 | November 12, 2025 | October 2, 2025 | 41d | ENC. 682/50LVBC $750,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $500,000 |
| 86 | November 12, 2025 | October 2, 2025 | 41d | ENC. 682/50WVKM $1,818,182 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $316,865 |
| 87 | November 12, 2025 | September 4, 2025 | 69d | ENC. 682/50LVBC $750,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $250,000 |
| 88 | November 12, 2025 | October 2, 2025 | 41d | INC ENC 50RLDS $36,398.57 FOR CO #'S24 & 31; $116,274.55 CO14, 34&35 | $202,329 |
| 89 | November 12, 2025 | October 2, 2025 | 41d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $178,404 |
| 90 | November 12, 2025 | October 2, 2025 | 41d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $111,348 |
| 91 | November 19, 2025 | November 5, 2025 | 14d | PMT#25, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $100 |
| 92 | November 24, 2025 | November 5, 2025 | 19d | PMT#25, SZC14224 | $17,895 |
| 93 | November 25, 2025 | November 5, 2025 | 20d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $30,506 |
| 94 | December 12, 2025 | November 5, 2025 | 37d | INC ENCR $1060045.15 CO#19,20 &30 WO#E700235F-SIXTH STREET VIADUCT-PARC | $457,165 |
| 95 | December 12, 2025 | November 5, 2025 | 37d | INC ENC CL13, AL1 ENCUMBER 298/50RLDS $57,885 FOR CHANGE ORDER #'S 54, 60&61 | $2,994 |
| 96 | December 23, 2025 | December 5, 2025 | 18d | PMT#26, ESCROW NO. 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $1,885 |
| 97 | December 30, 2025 | December 5, 2025 | 25d | PMT#26, SZC14224 | $19,817 |
| 98 | January 21, 2026 | December 5, 2025 | 47d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $88,977 |
| 99 | January 26, 2026 | December 31, 2025 | 26d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $204,393 |
| 100 | January 26, 2026 | December 31, 2025 | 26d | PMT#27, SZC14224 | $66,212 |
| 101 | January 26, 2026 | December 31, 2025 | 26d | PMT#27, ESCROW# 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $3,485 |
| 102 | March 10, 2026 | February 6, 2026 | 32d | PMT#28, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $10,888 |
| 103 | March 11, 2026 | February 6, 2026 | 33d | PMT#28, SZC14224 | $206,867 |
| 104 | April 17, 2026 | April 1, 2026 | 16d | PMT#30, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, INC, SZC14224 | $1,602 |
| 105 | April 21, 2026 | April 1, 2026 | 20d | PMT#30, SZC14224 | $30,440 |
| 106 | April 29, 2026 | April 15, 2026 | 14d | PMT#30, WO#E700235F, SIXTH ST VIADUCT-PARC 2/27/26-3/31/26, C144066 | $53,520 |
| 107 | May 11, 2026 | April 1, 2026 | 40d | ENC. 682/50NVCC $1,125,000 NTP 1 WO# E700235F FOR SIXTH STREET VIADUCT | $106,948 |
| 108 | May 21, 2026 | May 4, 2026 | 17d | PMT#31, SZC14224 | $61,845 |
| 109 | May 21, 2026 | May 4, 2026 | 17d | PMT#31, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $3,255 |
| 110 | June 11, 2026 | June 9, 2026 | 2d | PMT#31, CO#8, WO#E700235F, SIXTH ST VIADUCT-PARC 4/1/26-4/30/26, C144066 | $50,582 |
| 111 | June 11, 2026 | June 9, 2026 | 2d | PMT#31, CO#8, WO#E700235F, SIXTH ST VIADUCT-PARC 4/1/26-4/30/26, C144066 | $998 |
| 112 | June 17, 2026 | May 22, 2026 | 26d | PMT#32, SZC14224 | $312,703 |
| 113 | June 17, 2026 | May 22, 2026 | 26d | PMT#32, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING, SZC14224 | $15,452 |
| 114 | June 17, 2026 | May 22, 2026 | 26d | PMT#32, SZC14224 | $890 |
| 115 | July 8, 2026 | June 16, 2026 | 22d | PMT#32, CO#19, WO#E700235F, SIXTH ST VIADUCT-PARC | $101,165 |
| 116 | July 8, 2026 | June 16, 2026 | 22d | PMT#32, CO#8, WO#E700235F, SIXTH ST VIADUCT-PARC | $998 |
| 117 | July 28, 2026 | July 8, 2026 | 20d | PMT#33, ESCROW NO 2199 FOR LOS ANGELES ENGINEERING INC, SZC14224 | $444 |
| 118 | July 29, 2026 | July 8, 2026 | 21d | PMT#33, SZC14224 | $8,436 |
| 119 | August 21, 2026 | August 3, 2026 | 18d | PMT#34, WO#E700235F, SIXTH ST VIADUCT-PARC, 7/1/26-7/30/26, C144066 | $145,922 |
| 120 | August 21, 2026 | August 3, 2026 | 18d | PMT#34, CO#54, WO#E700235F, SIXTH ST VIADUCT-PARC 7/1/26-7/30/26, C144066 | $3,313 |