What has the City paid on purchase order SC50CO24134474M?

$1.47M paid to Kleinfelder, Inc across 17 payments from April 11, 2024 to January 21, 2025, charged to Non-Departmental / 2nd St Tunnel Rehabilitation.

What it was for

2nd St Tunnel Rehabilitation

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Road Maintenance and Rehabilitation Program Special Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1April 11, 2024April 10, 20241d206/50/50WKJT TOS 203 NTP1$40,305
2July 9, 2024June 18, 202421d206/50/50WKJT TOS 203 NTP1$85,642
3July 12, 2024June 18, 202424d206/50/50WKJT TOS 203 NTP1$79,925
4July 15, 2024June 13, 202432d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$26,194
5July 18, 2024June 5, 202443d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$121,572
6July 29, 2024June 27, 202432d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$53,502
7July 30, 2024July 26, 20244d206/50/50WKJT TOS 203 NTP1$11,062
8August 1, 2024July 23, 20249d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$61,217
9August 20, 2024August 5, 202415d206/50/50WKJT TOS 203 NTP1$6,729
10September 3, 2024August 23, 202411d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$62,599
11October 7, 2024September 23, 202414d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$161,304
12November 5, 2024October 31, 20245d206/50/50WKJT TOS 203 NTP1$10,141
13November 5, 2024October 31, 20245d206/50/50WKJT E1909017 TOS 203 NTP 2 CO#1$7,119
14November 13, 2024October 29, 202415d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$153,441
15January 15, 2025December 16, 202430d206/50/50WKJT E1909017 TOS 203 NTP 2 CO#1$7,852
16January 15, 2025December 16, 202430d206/50/50WKJT TOS 203 NTP1$1,180
17January 21, 2025December 18, 202434d$963,514 TOS 205 NTP1 & 2 2ND STREET TUNNEL REHAB & RECONSTR E1908982 59/50WVGJ$576,158

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.