SpendingContractsPurchase order

What has the City paid on purchase order SC50CO24124509M?

$2.72M paid to Los Angeles Conservation Corps Inc across 41 payments from May 30, 2024 to February 24, 2026, charged to Non-Departmental / Tree Planting Projects.

What it was for

Tree Planting Projects

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Environmental Affairs Trust

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1May 30, 2024January 26, 2024125dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 AUG23 NTP2$29,986
2May 30, 2024December 22, 2023160dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUL23 NTP2$27,598
3June 4, 2024May 30, 20245d537/50/50VMGF GREENFILTRATION$61,416
4June 18, 2024January 30, 2024140dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 OCT23 NTP2$80,237
5June 18, 2024January 31, 2024139dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 NOV23 NTP2$69,066
6June 21, 2024January 30, 2024143dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 SEPT23 NTP2$85,682
7July 29, 2024June 11, 202448d537/50/50VMGF GREENFILTRATION$11,631
8July 29, 2024May 13, 202477d537/50/50VMGF GREENFILTRATION$7,560
9August 5, 2024April 12, 2024115dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 DEC23 NTP2$67,376
10August 28, 2024July 17, 202442d537/50/50VMGF GREENFILTRATION$15,120
11October 3, 2024July 16, 202479dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 FEB24 NTP2$60,667
12November 22, 2024July 23, 2024122dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 APR24 NTP2REV$158,290
13November 26, 2024July 16, 2024133dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JAN24 NTP2$45,143
14December 18, 2024July 18, 2024153dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAR24 NTP2$72,240
15December 27, 2024August 26, 2024123dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAY24 NTP2$106,090
16January 17, 2025August 30, 2024140dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUN24 NTP2$39,519
17March 12, 2025November 12, 2024120dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 AUG24 NTP2$99,181
18March 12, 2025November 15, 2024117dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUL24 NTP2$57,791
19March 18, 2025November 15, 2024123dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 AUG24 NTP2BUDMOD$70,141
20March 18, 2025February 7, 202539dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 NOV24 NTP2$18,387
21March 25, 2025January 16, 202568dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 AUG-SEP24 NTP6$59,960
22March 27, 2025January 24, 202562dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 NO24 NTP6$148,291
23March 27, 2025January 24, 202562dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 OCT24 NTP6$109,410
24April 4, 2025February 7, 202556dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 SEP24 NTP6-LABOR$167,335
25June 13, 2025March 19, 202586dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUL-SEP24 NTP7-LABOR$83,561
26June 18, 2025March 18, 202592dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 DEC24 NTP6$122,537
27September 25, 2025June 10, 2025107dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAR25 NTP6$144,340
28November 6, 2025April 14, 2025206dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 DEC24 NTP2$12,802
29November 6, 2025September 19, 202548dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUN25 NTP6-A1$6,558
30November 7, 2025September 17, 202551dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JAN25 NTP6$102,193
31November 7, 2025September 17, 202551dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 FEB25 NTP6$54,344
32December 4, 2025September 30, 202565dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 APR-25 NTP7$52,214
33December 4, 2025September 30, 202565dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUN25 NTP7$42,387
34December 5, 2025September 23, 202573dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 APR25 NTP6$48,094
35December 26, 2025September 19, 202598dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 OCT24-FEB25 NTP7-LABOR$139,111
36December 30, 2025October 1, 202590dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAY-25 NTP7$84,724
37December 30, 2025September 23, 202598dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAR-25 NTP7$8,901
38January 14, 2026December 31, 202514dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 JUN25 NTP6$59,434
39January 15, 2026December 31, 202515dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAR-JUN25 NTP2$23,393
40February 13, 2026January 22, 202622dLACC-F834/50/50OOFC-AMD#28-INV#05-1216 MAY25 NTP6$66,061
41February 24, 2026February 19, 20265d537/50/50VMGF GREENFILTRATION$2,240

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.