SpendingContractsPurchase order

What has the City paid on purchase order SC50CO23134271M?

$1.74M paid to Exp U.S. Services Inc. across 27 payments from October 11, 2023 to June 15, 2026, charged to Non-Departmental / Kinney Street Improvement BTWN Crestmoore Pl and Lavell Dr.

What it was for

Kinney Street Improvement BTWN Crestmoore Pl and Lavell Dr

Budget line carrying the most money, of 5 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Road Maintenance and Rehabilitation Program Special Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1October 11, 2023September 13, 202328dTOS2 E1908262 7TH ST STREETSCAPE 59V/50/50RKHV NTP 1 $ 300,000$122,676
2October 11, 2023September 13, 202328dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS NTP 1 $ 100,000$35,214
3October 11, 2023September 13, 202328dTOS2 E1908239 NATIONAL BLVD AT CLARINGTON 59V/50/50VVGP NTP 1 $ 200,000$10,009
4October 19, 2023September 13, 202336dTOS2 E1908262 7TH ST STREETSCAPE 59V/50/50RKHV NTP 1 $ 300,000$48,105
5October 19, 2023September 13, 202336dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS NTP 1 $ 100,000$16,027
6January 3, 2024December 11, 202323dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS NTP 1 $ 100,000$29,622
7January 8, 2024December 11, 202328dTOS2 E1908262 7TH ST STREETSCAPE 59V/50/50RKHV NTP 1 $ 300,000$58,671
8January 12, 2024December 11, 202332dTOS2 E1908239 NATIONAL BLVD AT CLARINGTON 59V/50/50VVGP NTP 1 $ 200,000$75
9May 9, 2024April 10, 202429dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS NTP 1 $ 100,000$120,605
10May 9, 2024April 10, 202429dTOS2 E1908262 7TH ST STREETSCAPE 59V/50/50RKHV NTP 1 $ 300,000$70,548
11June 17, 2024April 10, 202468d$232,410 CL3,AL1 NTP 4(PART) E1908262 59V/50RKHV$232,410
12October 15, 2024October 9, 20246dTOS2/50/41A/50WKJW/E1908262/NTP4$60,870
13November 21, 2024April 10, 2024225dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS NTP 1 $ 100,000$1,051
14December 2, 2024October 21, 202442dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS NTP 1 $ 100,000$111,672
15January 13, 2025December 11, 202433dTOS#2/NTP4/50WKJW_7TH ST STREETSCAPE_1/4-2/9/24$80,872
16February 26, 2025February 20, 20256dTOS#2/NTP4/50WKJW_7TH ST STREETSCAPE_7/1-8/2/24$20,350
17March 3, 2025February 6, 202525dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$391,779
18April 10, 2025April 7, 20253dTOS2/NTP/50WKJW_7THST STREETSCAPE_10/31/23-9/3/24$20,279
19May 19, 2025May 8, 202511dF41A/50WKJW/E1908262_INV#150012/8 VER.2$32
20July 14, 2025June 9, 202535dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$89,366
21February 11, 2026December 24, 202549dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$20,312
22February 11, 2026December 24, 202549dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50YVII$953
23February 23, 2026August 4, 2025203dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$37,225
24February 23, 2026August 4, 2025203dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50YVII$31,821
25March 9, 2026December 2, 202597dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$77,537
26May 13, 2026April 9, 202634dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$27,032
27June 15, 2026June 1, 202614dTOS2 E1908478 KINNEY ST. IMPROVEMENT 59V/50/50RKHS$28,650

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.