SpendingContractsPurchase order

What has the City paid on purchase order SC50CO23129642M?

$976K paid to 2 different vendors (the largest, Atkins North America, Inc., received $521.3K) across 31 payments from August 31, 2023 to March 24, 2026, charged to Non-Departmental / Wilmington Q Street Local Urban Area Flow Management Project.

A blanket order, not one firm's contract

2 different vendors draw against this purchase order, so the $976K above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

Approval records

  • Contract C-129642Award recorded in the City's procurement portal; see below.

Paid from

Measure W - Safe, Clean Water - Regional Projects SF

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Awarded and paid so far

The City's procurement portal, RAMP, records contract C-129642 (the number embedded in this order's number, SC50CO23129642M) as awarded to Atkins North America, Inc. for $1.2M (task order solicitation), effective July 11, 2017 and expiring July 11, 2027. This order has paid $975.5K, 81% of that figure.

The award amount and dates are as entered in RAMP; later amendments that change a contract's ceiling or term are not always reflected there, and a contract can be paid through orders not shown on this page. RAMP title: “TOS 60 - Union Pacific Pumping Plant No. 602 Rehabilitation”. See the award on RAMP

Paid to

Atkins North America, Inc.$521K · 13 payments
Atkinsrealis USA Inc$454K · 18 payments

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 31, 2023June 28, 202364d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$80,000
2September 14, 2023August 17, 202328d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$27,578
3September 25, 2023August 17, 202339d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$7,794
4October 16, 2023October 5, 202311d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$111,733
5October 30, 2023October 13, 202317d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$24,498
6January 3, 2024November 28, 202336d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$47,632
7March 14, 2024January 25, 202449d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$20,477
8June 13, 2024April 10, 202464d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$15,000
9November 21, 2024September 24, 202458d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$48,486
10November 21, 2024September 24, 202458d63F-50VABW-S34WWQGS-TOS 66-NTP#2 WILMINGTON Q PROJECT$4,359
11January 7, 2025November 15, 202453d63F-50VABW-S34WWQGS-TOS 66-NTP#2 WILMINGTON Q PROJECT$41,788
12February 10, 2025January 21, 202520d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$46,657
13April 14, 2025March 3, 202542d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$45,346
14June 12, 2025April 7, 202566d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$65,751
15July 23, 2025May 29, 202555d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$36,774
16October 29, 2025May 14, 2025168d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$73,051
17October 29, 2025July 7, 2025114d63F-50VABW-S34WWQGS-TOS 66-NTP#3 WILMINGTON Q PROJECT$29,851
18October 29, 2025July 30, 202591d63F-50VABW-S34WWQGS-TOS 66-NTP#5 WILMINGTON Q PROJECT$27,000
19October 29, 2025July 7, 2025114d63F-50VABW-S34WWQGS-TOS 66-NTP#5 WILMINGTON Q PROJECT$7,433
20October 29, 2025July 7, 2025114d63F-50VABW-S34WWQGS-TOS 66-NTP#2 WILMINGTON Q PROJECT$6,698
21October 29, 2025July 7, 2025114d63F-50VABW-S34WWQGS-TOS 66-NTP#1 WILMINGTON Q STREET LOCAL AREA URBAN FLOW MGNT PROJECT$5,473
22November 5, 2025September 10, 202556d63F-50VABW-S34WWQGS-TOS 66-NTP#5 WILMINGTON Q PROJECT$44,377
23November 18, 2025August 31, 202579d63F-50VABW-S34WWQGS-TOS 66-NTP#5 WILMINGTON Q PROJECT$42,427
24November 21, 2025October 30, 202522d63F-50VABW-S34WWQGS-TOS 66-NTP#5 WILMINGTON Q PROJECT$40,485
25February 12, 2026December 11, 202563d63F-50VABW-S34WWQGS-TOS 66-NTP#5 WILMINGTON Q PROJECT$21,759
26February 12, 2026December 11, 202563dDRAFT BR -ATKINS NORTH AMERICA_C129642_TOS SN 66$2,551
27February 26, 2026December 22, 202566d63F_50VABW_S34WWQGS_TOS 66_NTP#6$17,048
28March 19, 2026January 26, 202652d63F_50VABW_S34WWQGS_TOS 66_NTP#6$9,000
29March 24, 2026February 27, 202625d63F_50VABW_S34WWQGS_TOS 66_NTP#6$16,138
30March 24, 2026February 27, 202625d63F_50VABW_S34WWQGS_TOS 66_NTP#7$4,280
31March 24, 2026February 27, 202625d63F_50VABW_S34WWQGS_TOS 66_NTP#8$4,081

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. Award from RAMP Opportunity Awards (h8mw-iegk), matched on the contract number embedded in this order's number and on the vendor's name. The City's biggest contracts · The checkbook.