What has the City paid on purchase order SC50CO22139368K?
$5.26M paid to International Line Builders Inc across 36 payments from April 28, 2022 to February 2, 2026, charged to Non-Departmental / Vision Zero Corridor Projects - SB1.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Road Maintenance and Rehabilitation Program Special Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Non-Departmental
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | April 28, 2022 | April 15, 2022 | 13d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $93,535 |
| 2 | April 29, 2022 | March 15, 2022 | 45d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $132,464 |
| 3 | May 23, 2022 | May 16, 2022 | 7d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $221,649 |
| 4 | June 17, 2022 | June 14, 2022 | 3d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $176,971 |
| 5 | July 20, 2022 | July 14, 2022 | 6d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $159,686 |
| 6 | August 23, 2022 | August 15, 2022 | 8d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $345,547 |
| 7 | August 31, 2022 | August 26, 2022 | 5d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $54,404 |
| 8 | September 22, 2022 | September 13, 2022 | 9d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $433,449 |
| 9 | October 19, 2022 | October 14, 2022 | 5d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $310,496 |
| 10 | November 22, 2022 | November 17, 2022 | 5d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $230,919 |
| 11 | December 23, 2022 | December 15, 2022 | 8d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $231,600 |
| 12 | December 29, 2022 | December 15, 2022 | 14d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $23,500 |
| 13 | January 24, 2023 | January 17, 2023 | 7d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $230,503 |
| 14 | January 26, 2023 | January 17, 2023 | 9d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $19,392 |
| 15 | February 27, 2023 | February 17, 2023 | 10d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $135,112 |
| 16 | March 22, 2023 | March 16, 2023 | 6d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $78,514 |
| 17 | March 30, 2023 | March 16, 2023 | 14d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $5,672 |
| 18 | April 21, 2023 | April 18, 2023 | 3d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $108,402 |
| 19 | May 24, 2023 | May 18, 2023 | 6d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $179,938 |
| 20 | May 26, 2023 | May 18, 2023 | 8d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $6,978 |
| 21 | June 21, 2023 | June 16, 2023 | 5d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $240,754 |
| 22 | July 25, 2023 | July 14, 2023 | 11d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $220,224 |
| 23 | August 17, 2023 | August 15, 2023 | 2d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $301,648 |
| 24 | September 21, 2023 | September 15, 2023 | 6d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $207,593 |
| 25 | October 23, 2023 | October 16, 2023 | 7d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $318,167 |
| 26 | November 17, 2023 | November 15, 2023 | 2d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $162,838 |
| 27 | December 28, 2023 | December 18, 2023 | 10d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $79,460 |
| 28 | January 25, 2024 | January 22, 2024 | 3d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $31,506 |
| 29 | March 4, 2024 | February 14, 2024 | 19d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $13,259 |
| 30 | April 4, 2024 | March 15, 2024 | 20d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $10,241 |
| 31 | July 22, 2024 | June 20, 2024 | 32d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $178,681 |
| 32 | October 17, 2024 | October 10, 2024 | 7d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $144,595 |
| 33 | October 29, 2024 | October 10, 2024 | 19d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $5,724 |
| 34 | March 3, 2025 | February 4, 2025 | 27d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $36,979 |
| 35 | April 10, 2025 | March 13, 2025 | 28d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $33,784 |
| 36 | February 2, 2026 | January 26, 2026 | 7d | E1908828 VISION ZERO PHASE 2E TRAFFIC SIGNAL 59V/50/50TKGD $5,115,034 NTP DTD 11/09/21 | $99,921 |