What has the City paid on purchase order SC50CO22138505K?

$5.79M paid to Mike Prlich & Sons Inc across 86 payments from October 22, 2021 to June 14, 2024, charged to Non-Departmental / Arroyo Seco Urban Runoff Project No 2.

What it was for

Arroyo Seco Urban Runoff Project No 2

Budget line carrying the most money, of 6 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Measure W - Safe, Clean Water - Municipal Program SF

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1October 22, 2021October 5, 202117d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$147,082
2October 22, 2021October 5, 202117d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$57,732
3November 5, 2021October 29, 20217d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$288,570
4November 5, 2021October 29, 20217d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$203,831
5November 5, 2021October 29, 20217d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$7,113
6December 8, 2021November 29, 20219d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$56,652
7December 8, 2021November 29, 20219d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$34,602
8December 8, 2021November 29, 20219d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$22,393
9December 10, 2021November 29, 202111d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$854
10February 7, 2022January 31, 20227d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$514,320
11February 7, 2022January 31, 20227d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$106,599
12February 7, 2022December 27, 202142d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$16,386
13February 7, 2022December 27, 202142d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$15,199
14February 16, 2022December 27, 202151d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$9,500
15March 7, 2022February 28, 20227d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$25,650
16March 8, 2022February 28, 20228d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$462,058
17March 8, 2022February 28, 20228d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$144,867
18April 8, 2022March 31, 20228d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$193,373
19April 8, 2022March 31, 20228d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$132,862
20April 8, 2022March 31, 20228d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$23,429
21May 12, 2022April 29, 202213d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$160,849
22May 12, 2022April 29, 202213d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$113,556
23May 12, 2022April 29, 202213d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$34,344
24June 8, 2022May 31, 20228d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$47,452
25June 8, 2022May 31, 20228d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$45,765
26June 8, 2022May 31, 20228d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$28,761
27June 8, 2022May 31, 20228d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$18,481
28August 18, 2022August 5, 202213d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$88,177
29August 18, 2022August 5, 202213d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$66,760
30August 18, 2022August 5, 202213d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$40,754
31August 18, 2022August 5, 202213d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$2,332
32September 22, 2022September 14, 20228d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$91,059
33September 22, 2022September 14, 20228d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$53,327
34September 22, 2022September 14, 20228d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$42,125
35September 22, 2022September 14, 20228d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$4,757
36November 10, 2022October 12, 202229d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$272,844
37November 10, 2022October 12, 202229d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$105,702
38November 10, 2022October 12, 202229d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$84,953
39November 10, 2022October 12, 202229d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$3,887
40November 21, 2022November 9, 202212d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$46,761
41November 21, 2022November 9, 202212d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$22,553
42November 21, 2022November 9, 202212d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$19,211
43November 21, 2022November 9, 202212d60W/50/50TAAB/S33WMARI; ARROYO SECO LFD PROJECT$11,133
44November 30, 2022November 9, 202221d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$89,030
45December 23, 2022December 15, 20228d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$163,803
46January 6, 2023December 15, 202222d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$38,661
47January 6, 2023December 15, 202222d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$24,556
48January 25, 2023December 15, 202241d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$7,870
49January 26, 2023January 17, 20239d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$335,150
50February 22, 2023February 13, 20239d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$138,514
51March 8, 2023March 6, 20232d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$47,338
52March 8, 2023March 6, 20232d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$26,174
53March 8, 2023March 6, 20232d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$21,468
54March 8, 2023March 6, 20232d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$18,594
55March 24, 2023March 17, 20237d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$280,866
56March 24, 2023March 17, 20237d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTR PROJ CO#26$5,251
57March 29, 2023March 17, 202312d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$11,816
58March 29, 2023March 17, 202312d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$4,320
59April 20, 2023April 13, 20237d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$88,280
60April 20, 2023April 13, 20237d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTR PROJ CO#26$1,188
61April 26, 2023April 13, 202313d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$30,285
62April 26, 2023April 13, 202313d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$16,219
63April 27, 2023April 13, 202314d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTR PROJ CO#26$30,600
64May 31, 2023May 12, 202319d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$23,500
65May 31, 2023May 12, 202319d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$12,657
66July 12, 2023June 29, 202313d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$10,257
67July 19, 2023June 29, 202320d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$17,282
68July 19, 2023June 29, 202320d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$13,999
69October 18, 2023October 10, 20238d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTR PROJ CO#26$38,203
70November 17, 2023October 31, 202317d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$28,263
71November 17, 2023October 31, 202317d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$17,058
72January 17, 2024January 5, 202412d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$17,791
73January 17, 2024January 5, 202412d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$9,011
74March 20, 2024March 7, 202413d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTR PROJ CO#26$33,013
75March 20, 2024March 7, 202413d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$24,166
76April 17, 2024March 7, 202441d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$1,986
77April 17, 2024March 7, 202441d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$1,847
78April 17, 2024March 7, 202441d60W/50/50TAAA/S33WFIGU; ARROYO SECO LFD PROJECT$1,350
79April 24, 2024April 8, 202416d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$5,068
80May 15, 2024April 8, 202437d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$2,122
81May 15, 2024April 8, 202437d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$2,074
82June 5, 2024May 30, 20246d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTRUCTION PROJECT$60,771
83June 5, 2024May 30, 20246d59V/50/50RKHR/E1908114; VIA MARISOL STREET RECONSTR PROJ CO#26,#28-29$5,698
84June 14, 2024May 30, 202415d60W/50/50VAAO/S33WMARI; ARROYO SECO LFD PROJECT$99,346
85June 14, 2024May 30, 202415d60W/50/50VAAV/S33WFIGU; ARROYO SECO LFD PROJECT$90,179
86June 14, 2024May 30, 202415d60W/50/50WAEB/S33WFIGU; ARROYO SECO LFD PROJECT$22,151

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.