What has the City paid on purchase order SC50CO22136182M?
$12.57M paid to Murray Plumbing and Heating Corp. across 69 payments from November 17, 2021 to January 12, 2026, charged to Non-Departmental / PW-Sanitation Expense and Equipment.
What it was for
PW-Sanitation Expense and Equipment
Budget line carrying the most money, of 5 this order is charged to.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Sewer Capital Fund
Department: Non-Departmental
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | November 17, 2021 | November 11, 2021 | 6d | INV#18140-005, C136182 07/11/21-08/09/21 | $1,559,294 |
| 2 | December 29, 2021 | December 1, 2021 | 28d | INV#18140-007, C136182 08/10/21-11/09/21 | $27,053 |
| 3 | January 24, 2022 | January 11, 2022 | 13d | INV#18140-004.1, 04/26/21 - 04/28/21 | $22,272 |
| 4 | January 31, 2022 | January 14, 2022 | 17d | INV#18140-005.1 ESOL, 07/11/21 - 09/27/21 | $2,188,350 |
| 5 | February 2, 2022 | January 14, 2022 | 19d | INV#18140-005.1 GGEN, 07/11/21 - 09/23/21 | $605,646 |
| 6 | February 2, 2022 | January 14, 2022 | 19d | INV#18140-005.1 CSEC, 07/11/21 - 09/23/21 | $586,340 |
| 7 | March 22, 2022 | March 11, 2022 | 11d | CONSTRUCTION OF TRAILER FOUNDATION-LOPEZ CANYON YARD-DECREASE BY $7,554.88 | $33,771 |
| 8 | March 22, 2022 | March 11, 2022 | 11d | CONSTRUCTION OF TRAILER FOUNDATION-DC TILLMANYARD-INCREASE BY $7,554.88 | $31,686 |
| 9 | April 11, 2022 | March 8, 2022 | 34d | INV#18140-005.2 ESOL, 09/28/21 - 12/15/21 | $1,599,942 |
| 10 | April 13, 2022 | April 6, 2022 | 7d | INV#18140-003, SZH11926, 03/09/21 - 04/03/21 | $71,074 |
| 11 | May 31, 2022 | May 10, 2022 | 21d | INV#18140-011, 12/01/21 - 02/25/22 | $58,477 |
| 12 | May 31, 2022 | May 10, 2022 | 21d | INV#18140-011.1, 03/04/22 - 04/01/22 | $14,181 |
| 13 | June 2, 2022 | May 31, 2022 | 2d | 488/50/50VX82 | $7,403 |
| 14 | June 2, 2022 | May 31, 2022 | 2d | 488/50/50VX82 | $4,069 |
| 15 | June 14, 2022 | May 23, 2022 | 22d | INV#18140-012, PROJ#HX0000003, 12/03/21-05/13/22 | $29,777 |
| 16 | July 19, 2022 | July 1, 2022 | 18d | INV#18140-005.3 ESOL, PROJ #: HX0000003, 11/29/21 - 02/10/22 | $1,432,049 |
| 17 | July 26, 2022 | July 14, 2022 | 12d | INV#18140-010, PROJ #DX0000006, 11/10/21 - 11/18/21 | $25,553 |
| 18 | October 7, 2022 | September 19, 2022 | 18d | INV#18140-014, SZH12138, 02/01/22 - 06/30/22 | $340,200 |
| 19 | October 12, 2022 | September 19, 2022 | 23d | INV#18140-005.3 CSEC, 12/16/21 - 07/25/22 | $200,103 |
| 20 | October 12, 2022 | September 19, 2022 | 23d | INV#18140-005-.4 CSEC, 02/11/22 - 04/27/22 | $126,669 |
| 21 | October 12, 2022 | September 19, 2022 | 23d | IINV#18140-005.3 GGEN, 12/16/21 - 02/10/22 | $62,728 |
| 22 | October 14, 2022 | September 19, 2022 | 25d | INV#18140-005.4 GGEN, 02/11/22 - 04/27/22 | $44,158 |
| 23 | October 26, 2022 | September 22, 2022 | 34d | INV#18140-014.1, 04/01/22 - 06/30/22 | $31,605 |
| 24 | October 27, 2022 | September 26, 2022 | 31d | INV#18140-005.5 CSEC, 04/07/22 - 07/01/22 | $18,119 |
| 25 | November 3, 2022 | September 26, 2022 | 38d | INV#18140-005.5 GGEN, 03/29/22 - 07/01/22 | $20,039 |
| 26 | November 3, 2022 | September 28, 2022 | 36d | INV#18140-016, 08/12/22 - 08/31/22 | $18,653 |
| 27 | November 3, 2022 | September 22, 2022 | 42d | INV#18140-005.6 GGEN, 03/07/22 - 03/11/22 | $13,481 |
| 28 | November 4, 2022 | September 26, 2022 | 39d | INV#18140-005.4 ESOL, 01/06/22 - 04/01/22 | $1,038,223 |
| 29 | November 4, 2022 | September 26, 2022 | 39d | INV#18140-005.5 ESOL, 02/07/22 - 07/01/22 | $352,798 |
| 30 | November 10, 2022 | October 6, 2022 | 35d | INV#18140-005.6 ESOL, 04/04/22 - 07/01/22 | $319,443 |
| 31 | November 17, 2022 | October 17, 2022 | 31d | INV#18140-014.2, SZH12138, 05/01/22 - 05/31/22 | $10,710 |
| 32 | December 28, 2022 | November 16, 2022 | 42d | INV#18140-014.3, FENCELINE MONITORING, 9/14/22 - 10/31/22 | $11,970 |
| 33 | January 13, 2023 | December 8, 2022 | 36d | INV#18140-014.4, FENCELINE MONITORING, 09/01/22 - 10/10/22 | $6,786 |
| 34 | February 10, 2023 | January 20, 2023 | 21d | INV#18140-015, TC0000019, 07/05/22 - 11/08/22 | $9,799 |
| 35 | April 5, 2023 | March 28, 2023 | 8d | INCREASE FOR DOUBLE WIDE TRAILER SETTING LOPEZ CANYON YARD | $4,135 |
| 36 | April 14, 2023 | April 5, 2023 | 9d | ELECTRICAL WORK, TRAILER SETTING &LID PLANTER BOX INSTL -LOPEZ CANYON | $49,257 |
| 37 | April 26, 2023 | April 5, 2023 | 21d | INV#18140-014.6, PROJ HC0000025, 07/01/22 - 12/31/22 | $135,920 |
| 38 | April 28, 2023 | April 5, 2023 | 23d | INV#18140-014.7, PROJ NO: HC0000025, 01/31/23 - 02/28/23 | $28,140 |
| 39 | May 3, 2023 | April 25, 2023 | 8d | CONSTRUCTION OF TRAILER FOUNDATION-CAZADOR YARD | $255,556 |
| 40 | May 3, 2023 | April 25, 2023 | 8d | FOUNDATION-CAZADOR TRAILER | $101,858 |
| 41 | May 12, 2023 | April 26, 2023 | 16d | FOUNDATION-CAZADOR TRAILER | $4,200 |
| 42 | May 12, 2023 | April 25, 2023 | 17d | FOUNDATION-CAZADOR TRAILER | $4,189 |
| 43 | May 18, 2023 | April 21, 2023 | 27d | INV#18140-015.2, PROJECT TC0000019, 11/09/22 - 03/29/23 | $55,727 |
| 44 | May 24, 2023 | May 16, 2023 | 8d | TRAILER SETTING, LID PLANTER BOX INSTL & FRESH WATER TIE-IN -DC TILLMAN | $240,505 |
| 45 | May 30, 2023 | May 18, 2023 | 12d | ELECTRICAL WORK, TRAILER SETTING &LID PLANTER BOX INSTL -LOPEZ CANYON | $136,613 |
| 46 | July 26, 2023 | July 10, 2023 | 16d | INV#18140-014.8, PROJ#HC0000025, 03/01/23 - 04/30/23 | $46,053 |
| 47 | September 5, 2023 | June 21, 2023 | 76d | FOUNDATION-CAZADOR TRAILER | $52,860 |
| 48 | September 8, 2023 | August 17, 2023 | 22d | INV#18140-005.9 ESOL, PROJ#HX0000003, 12/09/22 | $4,540 |
| 49 | September 22, 2023 | August 25, 2023 | 28d | ELECTRICAL WORK, TRAILER SETTING &LID PLANTER BOX INSTL -LOPEZ CANYON | $24,781 |
| 50 | September 22, 2023 | August 25, 2023 | 28d | TRAILER SETTING, LID PLANTER BOX INSTL & FRESH WATER TIE-IN -DC TILLMAN | $9,837 |
| 51 | September 22, 2023 | August 25, 2023 | 28d | TRAILER SETTING, LID PLANTER BOX INSTL & FRESH WATER TIE-IN -DC TILLMAN | $3,387 |
| 52 | September 29, 2023 | September 27, 2023 | 2d | 488/50/50VX82 ADDITIONAL ENCUMBRANCE | $10,147 |
| 53 | November 15, 2023 | September 28, 2023 | 48d | INV#18140-005.10 ESOL, PROJ#HX0000003, 12/01/22 | $2,560 |
| 54 | November 27, 2023 | September 28, 2023 | 60d | INV#18140-014.9, PROJ#HC0000025, 05/01/23 - 06/30/23 | $26,985 |
| 55 | December 28, 2023 | November 1, 2023 | 57d | ELECTRICAL WORK, TRAILER SETTING &LID PLANTER BOX INSTL -LOPEZ CANYON | $180,520 |
| 56 | April 2, 2024 | March 20, 2024 | 13d | 488/50/50VX82 | $35,305 |
| 57 | April 2, 2024 | March 20, 2024 | 13d | 488/50/50VX82 ADDITIONAL ENCUMBRANCE | $6,208 |
| 58 | June 4, 2024 | May 7, 2024 | 28d | INV#18140-005 OH, 07/11/21 - 09/14/22 | $101,975 |
| 59 | June 4, 2024 | May 7, 2024 | 28d | INV#18140-005 OH, 07/11/21 - 09/14/22 | $76,899 |
| 60 | June 4, 2024 | May 7, 2024 | 28d | INV#18140-005 OH, 07/11/21 - 09/14/22 | $8,119 |
| 61 | June 5, 2024 | May 7, 2024 | 29d | INV#18140-004 OH, 04/26/21 - 04/28/21 | $914 |
| 62 | June 10, 2024 | May 8, 2024 | 33d | INV#18140-007 OH, 08/10/21-11/09/21 | $1,585 |
| 63 | June 13, 2024 | May 7, 2024 | 37d | INV#18140-016 OH, 08/01/22 - 11/30/22 | $8,330 |
| 64 | June 20, 2024 | May 17, 2024 | 34d | INV#18140-015 OH, 07/05/22 - 11/08/22 | $1,543 |
| 65 | July 19, 2024 | July 11, 2024 | 8d | 488/50/50VX82 ADDITIONAL ENCUMBRANCE | $22,489 |
| 66 | July 19, 2024 | July 11, 2024 | 8d | 488/50/50VX82 ADDITIONAL ENCUMBRANCE | $1,261 |
| 67 | April 23, 2025 | April 2, 2025 | 21d | INV#18140-010 OH, INDIRECT COSTS/PROFIT, 11/10/21 - 11/18/21 | $1,861 |
| 68 | April 23, 2025 | April 2, 2025 | 21d | INV#18140-010 OH, INDIRECT COSTS/PROFIT, 11/10/21 - 11/18/21 | $547 |
| 69 | January 12, 2026 | December 15, 2025 | 28d | INV#18140-015.3, ANDRITZ CENTRIFUGE TILE REPL, 10/02/2024 | $6,421 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.