SpendingContractsPurchase order

What has the City paid on purchase order SC50CO22124345M?

$4.11M paid to Geosyntec Consultants/C across 42 payments from August 25, 2021 to February 7, 2025, charged to Non-Departmental / San Fernando Valley Stormwater Capture Projects.

What it was for

San Fernando Valley Stormwater Capture Projects

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Landfill Closure & Postclosure

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 25, 2021April 1, 2021146dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$861,355
2August 25, 2021April 1, 2021146dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$426,500
3August 25, 2021April 1, 2021146dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$4,646
4August 26, 2021April 1, 2021147dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$306,200
5August 26, 2021April 1, 2021147dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$286,435
6August 26, 2021April 1, 2021147dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$263,250
7October 25, 2021April 13, 2021195dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$358,650
8October 25, 2021March 23, 2021216dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$233,400
9October 25, 2021March 23, 2021216dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$161,760
10October 25, 2021June 17, 2021130dTOS SN68:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT LANKERSHIM BLVD PROJECT.$152,709
11October 25, 2021April 13, 2021195dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$138,525
12October 25, 2021August 19, 202167dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$61,165
13October 25, 2021August 19, 202167dTOS SN97:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT AGNES AVE PROJECT.$56,500
14October 25, 2021August 19, 202167dTOS SN68:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT LANKERSHIM BLVD PROJECT.$43,275
15October 25, 2021August 19, 202167dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$36,681
16October 25, 2021June 17, 2021130dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$28,075
17October 25, 2021June 17, 2021130dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$24,675
18May 13, 2022May 3, 202210dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$47,375
19May 13, 2022May 3, 202210dTOS SN68:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT LANKERSHIM BLVD PROJECT.$44,625
20May 13, 2022May 3, 202210dTOS SN97:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT AGNES AVE PROJECT.$42,875
21May 13, 2022May 3, 202210dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$22,200
22May 13, 2022May 3, 202210dTOS SN68:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT LANKERSHIM BLVD PROJECT.$21,400
23May 13, 2022May 3, 202210dTOS SN97:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT AGNES AVE PROJECT.$13,625
24May 18, 2022May 12, 20226d488/50/50RLG2 TOS SN-117NTP 01/11/2021$10,101
25June 1, 2022May 26, 20226d488/50/50RLG2 TOS SN-117NTP 01/11/2021$4,996
26June 1, 2022May 26, 20226d488/50/50RLG2 TOS SN-117NTP 01/11/2021$2,976
27June 6, 2022May 20, 202217dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$44,769
28June 6, 2022May 20, 202217dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$41,875
29June 6, 2022May 20, 202217dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$19,550
30September 29, 2022September 21, 20228d488/50/50RLG2 TOS SN-117NTP 01/11/2021$9,198
31September 29, 2022August 30, 202230d488/50/50RLG2 TOS SN-117NTP 01/11/2021$4,483
32November 3, 2022July 11, 2022115dTOS SN98: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT VICTORY BLVD COLDWATER CANYON AVE PJ$55,375
33November 3, 2022July 11, 2022115dTOS SN68:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT LANKERSHIM BLVD PROJECT.$52,430
34November 3, 2022July 11, 2022115dTOS SN97:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT AGNES AVE PROJECT.$49,625
35November 3, 2022April 21, 2022196dTOS SN97:TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT AGNES AVE PROJECT.$5,975
36January 25, 2023July 11, 2022198dTOS SN99: TECHNICAL SVC FOR SAN FERNANDO VALLEY GREEN STREET AT GLENOAKS BLVD PROJECT.$48,625
37June 6, 2023June 1, 20235d488/50/50RLG2 TOS SN-117NTP 01/11/2021$5,527
38June 12, 2023June 6, 20236d488/50/50RLG2 TOS SN-117NTP 01/11/2021$49,713
39June 12, 2023June 6, 20236d488/50/50RLG2 TOS SN-117NTP 01/11/2021$5,726
40June 12, 2023June 6, 20236d488/50/50RLG2 TOS SN-117NTP 01/11/2021$1,872
41June 12, 2023June 6, 20236d488/50/50RLG2 TOS SN-117NTP 01/11/2021$1,747
42February 7, 2025January 23, 202515d488/50/50RLG2 TOS SN-117NTP 01/11/2021$58,784

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.