SpendingContractsPurchase order

What has the City paid on purchase order SC50CO20133006K?

$3.61M paid to Jilk Heavy Construction Inc. across 14 payments from February 10, 2020 to June 9, 2022, charged to Non-Departmental / Sidewalk Repair - Access Request Acceleration.

What it was for

Sidewalk Repair - Access Request Acceleration

Budget line carrying the most money, of 3 this order is charged to.

Approval records

  • Contract C-133006Stated in the order's descriptions.

Paid from

Special Gas Tax St Improv

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1February 10, 2020January 28, 202013dC-133006 JILK HEAVY CONSTRUCTION INC PCK#45 PR#1$96,808
2April 13, 2020March 16, 202028dE1908522 SRP #45 NTP DTD 10/15/19 59V/50/50RKGY$1,028,639
3May 21, 2020May 18, 20203dE1908522 SRP #45 NTP DTD 10/15/19 59V/50/50RKGY$24,602
4June 1, 2020May 5, 202027dNTP DTD 2/24/20 E1908645 ACCESS REQUEST ACCELERATION WORK PACKAGE 57$159,848
5June 10, 2020June 2, 20208dNTP DTD 2/24/20 E1908645 ACCESS REQUEST ACCELERATION WORK PACKAGE 57$426,317
6June 22, 2020June 16, 20206dNTP DTD 2/24/20 E1908645 ACCESS REQUEST ACCELERATION WORK PACKAGE 57$364,447
7June 22, 2020June 15, 20207dENCUMBRANCE-WO#E1908468 NTP DTD 1-9-2020 41A/50/50SBWW$33,981
8July 27, 2020July 17, 202010dNTP DTD 2/24/20 E1908642 ACCESS REQUEST ACCELERATION WORK PACKAGE 55$703,743
9August 14, 2020August 5, 20209dE1908471 CAVERA DR. (7280) NTP 1/28/20$154,779
10August 19, 2020August 11, 20208dNTP DTD 2/24/20 E1908645 ACCESS REQUEST ACCELERATION WORK PACKAGE 57$111,600
11September 1, 2020July 15, 202048dENCUMBRANCE-WO#E1908468 NTP DTD 1-9-2020 41A/50/50SBWW$210,360
12September 1, 2020July 15, 202048dENCUMBRANCE-WO#E1908468 NTP DTD 1-9-2020 41A/50/50SBWW$210,360
13January 14, 2022January 5, 20229d206/50/50VBWW E1908468 CO#3 DTD 12/29/21$81,817
14June 9, 2022June 6, 20223d206/50/50VBWW E1908468 CO#3 DTD 12/29/21$4,306

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.