What has the City paid on purchase order SC50CO19131649K?

$1.03M paid to Select Electric Inc across 21 payments from January 7, 2019 to July 15, 2025, charged to Non-Departmental / Riverside Dr Lighting Improvement Unit 1.

What it was for

Riverside Dr Lighting Improvement Unit 1

Budget line carrying the most money, of 2 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

St Lighting Maintenance Assess

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1January 7, 2019December 7, 201831dRIVERSIDE DRIVE LIGHTING IMPROVEMENT UNIT 1 CIP/STP-STPL-5006(823)$128,775
2January 7, 2019November 26, 201842dRIVERSIDE DRIVE LIGHTING IMPROVEMENT UNIT 1 CIP/STP-STPL-5006(823)$112,138
3January 24, 2019January 16, 20198dC131649 PP#3-WO#L1550086-RIVERSIDE DR LIGHTING IMP UNIT 1 CIP/STP ST LIGHTING PROJ$16,480
4February 25, 2019February 11, 201914dC131649 PP#4-WO#L1550086- RIVERSIDE DR LIGHTING IMP UNIT 1 CIP/STP ST LIGHTING PROJ$14,312
5March 27, 2019March 18, 20199dC131649 PP#5-WO#L1550086-RIVERSIDE DR LIGHTING IMP UNIT 1 CIP/STP ST LIGHTING PROJ$5,062
6April 9, 2019April 2, 20197dC131649-PP#6 / WO#L1550086-RIVERSIDE DR LIGHTING IMPR UNIT 1 CIP/STP ST LIGHTING PROJ$62,426
7May 10, 2019May 6, 20194dC131649-PP#7 / WO#L1550086-RIVERSIDE DR LIGHTING IMPR UNIT 1 CIP/STP ST LIGHTING PROJ$77,284
8June 14, 2019June 7, 20197dC131649-PP#8 WO#L1550086- RIVERSIDE DR LIGHTING IMPR UNIT 1 CIP/STP ST LIGHTING PROJ.$75,865
9July 23, 2019July 11, 201912dC131649-PP#9 WO#L1550086- RIVERSIDE DR LIGHTING IMPR UNIT 1 CIP/STP ST LIGHTING PROJ.$69,563
10July 30, 2019July 11, 201919dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#9$142,657
11August 8, 2019August 2, 20196dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#10$9,861
12September 13, 2019September 5, 20198dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#11$129,456
13October 21, 2019October 3, 201918dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#12$20,469
14April 2, 2020March 24, 20209dRIVERSIDE DRIVE LIGHTING IMPROVEMENT UNIT 1 CIP/STPSTPL-5006(823)$28,095
15April 8, 2020March 24, 202015dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#13$29,821
16April 10, 2020April 7, 20203dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#14$44,205
17February 3, 2021December 22, 202043dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#15$18,063
18November 23, 2021October 29, 202125dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#16F$21,695
19April 4, 2022March 2, 202233dC131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#17F$15,423
20October 26, 2023October 13, 202313dCO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#18$13,748
21July 15, 2025August 2, 2019—CO 131649 RIVERSIDE STREET IMPROV UNIT 1 CIP/STP - PR#10-$9,861

Download this table: ·

Draw-down shape

Sources