SpendingContractsPurchase order
What has the City paid on purchase order SC50CO19131555K?
$8.98M paid to Reyes Construction, Inc across 17 payments from November 6, 2018 to November 19, 2021, charged to Non-Departmental / Capital Infrastructure.
What it was for
Capital InfrastructureBudget line carrying the most money, of 3 this order is charged to.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Central LA Recycling TRFR Stat
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Non-Departmental
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | November 6, 2018 | September 27, 2018 | 40d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $147,187 |
| 2 | December 10, 2018 | November 27, 2018 | 13d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $244,578 |
| 3 | December 26, 2018 | December 13, 2018 | 13d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $834,611 |
| 4 | January 31, 2019 | January 16, 2019 | 15d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $1,895,295 |
| 5 | February 25, 2019 | February 13, 2019 | 12d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $1,326,462 |
| 6 | April 3, 2019 | March 15, 2019 | 19d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $619,706 |
| 7 | April 29, 2019 | April 12, 2019 | 17d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $740,733 |
| 8 | June 20, 2019 | June 17, 2019 | 3d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $68,514 |
| 9 | June 24, 2019 | June 17, 2017 | 737d | PYT #8; CLARTS STORMWATER & SAFETY IMPROV PH2 | $379,567 |
| 10 | July 26, 2019 | July 16, 2019 | 10d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $391,181 |
| 11 | October 11, 2019 | August 20, 2019 | 52d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $343,524 |
| 12 | March 1, 2021 | February 11, 2021 | 18d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $681,454 |
| 13 | July 19, 2021 | June 24, 2021 | 25d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $769,714 |
| 14 | July 19, 2021 | June 24, 2021 | 25d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $117,215 |
| 15 | July 22, 2021 | July 2, 2021 | 20d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $152,347 |
| 16 | July 22, 2021 | July 2, 2021 | 20d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $40,511 |
| 17 | November 19, 2021 | November 15, 2021 | 4d | CLARTS STORMWATER & SAFETY IMPROVEMENTS PROJ - PHASE 2 | $227,644 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.