SpendingContractsPurchase order

What has the City paid on purchase order SC50CO19130179K?

$6.16M paid to Colich & Sons LP across 26 payments from October 25, 2018 to October 27, 2025, charged to Non-Departmental / HWRP Emergency Primary Central Scrubber Facility Upgrades.

What it was for

HWRP Emergency Primary Central Scrubber Facility Upgrades

Budget line carrying the most money, of 4 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

WW Syst Comm Paper a Const FND

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1October 25, 2018September 13, 201842dENCUMBRANCE CO130179,508/50/50P997/S02PWTRL$291,887
2April 17, 2019April 1, 201916dENCUMBRANCE CO130179,508/50/50P997/S02PWTRL$56,971
3April 17, 2019April 2, 201915dENCUMBRANCE CO130179,508/50/50P997/S02PWTRL$18,361
4February 6, 2023December 13, 202255dPMT#1, SZH12146$301,315
5March 29, 2023December 19, 2022100dPMT#1, SZH12192$421,843
6March 29, 2023February 9, 202348dPMT#2, SZH12192$273,538
7March 29, 2023March 7, 202322dPMT#3, SZH12192$51,878
8May 9, 2023February 27, 202371dPMT#2, SZH12146$19,539
9June 12, 2023May 10, 202333dPMT#3, SZH12146$7,664
10December 6, 2023August 28, 2023100dPMT#4, SZH12192$1,222,365
11December 8, 2023August 24, 2023106dPMT#4, SZH12146$68,760
12January 3, 2024October 24, 202371dPMT#5, SZH12146$272,477
13February 8, 2024December 14, 202356dPMT#6, SZH12146$129,975
14February 9, 2024October 17, 2023115dPMT#5, SZH12192$611,183
15February 14, 2024January 3, 202442dPMT#6, SZH12192$842,160
16April 25, 2024April 1, 202424dPMT#7, SZH12192$330,567
17June 17, 2024May 8, 202440dPMT#7, HWRP EMER FLARE SYS REHAB, SZH12146$383,411
18October 15, 2024September 17, 202428dPMT#8, SZH12192$132,537
19October 28, 2024October 2, 202426dPMT#8 HWRP EMER FLARE SYS REHAB, SZH12146$166,744
20April 29, 2025April 14, 202515dPMT#9 HWRP EMER FLARE SYS REHAB, SZH12146$218,301
21May 23, 2025May 20, 20253dPMT#9F, SZH12192$60,093
22October 10, 2025August 27, 202544dPMT#10F RETN RELS CIP2518 HWRP EMER FLARE SYS REHAB, SZH12146$75,518
23October 27, 2025September 4, 202553dPMT#10F RETN RELS SZH12192$159,491
24October 27, 2025September 4, 202553dPMT 10F RETN RELS SZH12192$27,741
25October 27, 2025September 4, 202553dPMT#10F, RETN RELS SZH12192$13,091
26October 27, 2025September 4, 202553dPMT 10F, RETN RELS SZH12192$7,369

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.