SpendingContractsPurchase order

What has the City paid on purchase order SC50CO18129665M?

$2.79M paid to WSP USA Inc. across 60 payments from April 2, 2018 to April 10, 2026, charged to Non-Departmental / Taylor Yard G2 (Taylor Yard River Park).

What it was for

Taylor Yard G2 (Taylor Yard River Park)

Budget line carrying the most money, of 7 this order is charged to.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

MICLA Lease Rev Com Paper Ntes

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Non-Departmental

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1April 2, 2018March 20, 201813dCO129665 WSP TOS#13 E1908260 INV#AR 768459$176,385
2April 17, 2018March 5, 201843dCO129665 WSP TOS#13 E1908260 INV#AR 773464$214,686
3April 25, 2018March 2, 201854dPHASE II TAYLOR YARD CLEAN UP PROJECT$3,207
4April 25, 2018March 23, 201833dPHASE II TAYLOR YARD CLEAN UP PROJECT$2,190
5May 14, 2018March 22, 201853dPHASE II TAYLOR YARD CLEAN UP PROJECT$5,500
6May 15, 2018April 3, 201842d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK$117,379
7June 18, 2018April 20, 201859dPHASE II TAYLOR YARD CLEAN UP PROJECT$449
8June 22, 2018May 24, 201829dDESIGN ENGINEERING SERVICES, DCTWRP, TOS#22,SZD11276, 070117-051718$23,484
9August 10, 2018July 11, 201830dPHASE II TAYLOR YARD CLEAN UP PROJECT$1,919
10August 10, 2018July 11, 201830dPHASE II TAYLOR YARD CLEAN UP PROJECT$75
11September 7, 2018July 11, 201858d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK$81,079
12September 7, 2018July 11, 201858d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK$62,574
13December 20, 2018October 30, 201851d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK$268,579
14December 20, 2018October 30, 201851dPHASE II TAYLOR YARD CLEAN UP PROJECT$36,661
15January 23, 2019November 19, 201865dCO129665 TOS13 E1908260 INV.#02-28111B$109,107
16March 15, 2019January 17, 201957d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK$33,183
17March 15, 2019February 6, 201937d682/50/50PVCP/E1908260/TAYLOR YARD G2 RIVER PARK$30,309
18April 4, 2019March 1, 201934d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK NTP4$16,901
19May 21, 2019April 24, 201927d682/50/50PVCP/E1908260D/TAYLOR YARD G2 RIVER PARK NTP4$61,209
20June 18, 2019May 28, 201921d682/50/50PVCP/E1908260$28,040
21July 29, 2019July 12, 201917d682/50/50PVCP/E1908260$182,647
22August 5, 2019July 31, 20195dPHASE II TAYLOR YARD CLEAN UP PROJECT NTP#6$14,504
23September 25, 2019September 10, 201915d682/50/50PVCP/TOS13/E1908260$97,647
24September 25, 2019September 10, 201915d682/50/50PVCP/TOS13/E1908260$75,179
25October 16, 2019October 1, 201915d682/50/50PVCP/TOS13/E1908260$7,823
26April 24, 2020March 25, 202030d682/50/50PVCP/TOS13/E1908260$67,678
27December 16, 2020October 30, 202047d682/50/50PVCP/TOS13/E1908260$35,444
28December 16, 2020October 30, 202047d682/50/50PVCP/TOS13/E1908260$4,953
29December 28, 2020December 11, 202017d682/50/50PVCP/TOS13/E1908260$12,354
30June 21, 2023March 28, 202385d682/50/50SVEL/WO E1908260-TOS13-NTP#24R$29,975
31August 21, 2024August 8, 202413d16V/50VZAF/E1908260/NTP 36-39, 27R, 7R, 15, 16, 14R$183,722
32December 6, 2024November 26, 202410dTOS13/556/50/50RMTY/E1908260_1/25-8/2/24$28,317
33February 3, 2025January 29, 20255dBROWNFIELD CLEAN UP GRANT TAYLOR YARD G2 PROJECT$118,751
34February 3, 2025January 29, 20255dBROWNFIELD CLEAN UP GRANT TAYLOR YARD G2 PROJECT$361
35February 10, 2025August 24, 2024170d16V/50VZAF/E1908260/NTP 36-39, 27R, 7R, 15, 16, 14R$6,799
36February 10, 2025August 24, 2024170d16V/50VZAF/E1908260/NTP 30 TO 35$5,479
37February 27, 2025January 7, 202551dTOS13/556/50/50RMTY/E1908260_9/1 - 12/27/24$21,115
38February 27, 2025September 26, 2024154dTOS13/556/50/50RMTY/E1908260_8/3 - 8/30/24$7,081
39May 14, 2025May 9, 20255dINV#40133814_TOS13/F556/50RMTY$19,858
40May 14, 2025May 9, 20255dINV#40133813_TOS13/F556/50RMTY$2,127
41May 14, 2025May 9, 20255dINV#40133815_TOS13/F556/50RMTY$1,898
42May 14, 2025May 9, 20255dINV#40133816_TOS13/F556/50RMTY$491
43May 28, 2025January 7, 2025141d682/50/50PVCP/WO E1908260-TOS13-NTP#1$26,563
44May 28, 2025September 26, 2024244d682/50/50PVCP/WO E1908260-TOS13-NTP#1$13,046
45May 28, 2025January 7, 2025141d682/50/50PVCP/WO E1908260-TOS13-NTP#1$2,307
46June 5, 2025May 2, 202534d682/50/50PVCP/TOS13/E1908260$16,634
47June 5, 2025May 2, 202534d682/50/50PVCP/TOS13/E1908260$1,898
48June 5, 2025May 2, 202534d682/50/50PVCP/TOS13/E1908260$1,722
49August 13, 2025June 24, 202550d298/50WYRP/TOS 13/E1908260 NTP 41 &42$49,347
50August 13, 2025June 24, 202550d298/50WYRP/TOS 13/E1908260 NTP 41 &42$35,267
51September 18, 2025August 1, 202548d298/50WYRP/TOS 13/E1908260 NTP 41 &42$118,069
52September 18, 2025August 1, 202548dRQSC DRAFT BR-TAYLOR YARD G2, E1908532&1908260$104,008
53October 22, 2025August 29, 202554dRQSC DRAFT BR-TAYLOR YARD G2, E1908532&1908260$8,029
54November 12, 2025September 25, 202548dRQSC DRAFT BR-TAYLOR YARD G2, E1908532&1908260$11,484
55November 12, 2025September 25, 202548d298/50WYRP/TOS 13/E1908260 NTP 41 &42$7,594
56January 21, 2026November 3, 202579dRQSC DRAFT BR-TAYLOR YARD G2, E1908532&1908260$77,183
57January 21, 2026November 3, 202579d298/50WYRP/TOS 13/E1908260 NTP 41 &42$12,656
58February 12, 2026December 23, 202551dTOS 13 TAYLOR YARD G2 PARCEL$37,736
59February 12, 2026December 1, 202573dTOS 13 TAYLOR YARD G2 PARCEL$22,096
60April 10, 2026March 18, 202623dRQSC DRAFT BR-TAYLOR YARD G2, E1908532&1908260$43,309

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.