SpendingContractsPurchase order
What has the City paid on purchase order SC46CO22136500Y?
$35.00M paid to LA-Rics across 33 payments from October 28, 2021 to December 23, 2022, charged to Mayor / Los Angeles / Long Beach Region.
What it was for
Los Angeles / Long Beach RegionBudget line.
Order description, as published:
LA-RICS UASI 19 C-136500
Approval records
- Contract C-136500Stated in the order's descriptions.
Order dated October 26, 2021.
Paid from
FY19 Uasi Homeland Security Grant Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Mayor
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | October 28, 2021 | October 19, 2021 | 9d | LA-RICS UASI 19 C-136500 | $704,145 |
| 2 | October 28, 2021 | October 19, 2021 | 9d | LA-RICS UASI 19 C-136500 | $431 |
| 3 | January 11, 2022 | January 3, 2022 | 8d | LA-RICS UASI 19 C-136500 | $1,190,729 |
| 4 | April 7, 2022 | March 24, 2022 | 14d | LA-RICS UASI 19 C-136500 | $1,892,700 |
| 5 | April 7, 2022 | March 24, 2022 | 14d | LA-RICS UASI 19 C-136500 | $753,896 |
| 6 | April 7, 2022 | March 24, 2022 | 14d | LA-RICS UASI 19 C-136500 | $546,444 |
| 7 | April 7, 2022 | March 24, 2022 | 14d | LA-RICS UASI 19 C-136500 | $121,918 |
| 8 | June 1, 2022 | May 18, 2022 | 14d | LA-RICS UASI 19 C-136500 | $259,358 |
| 9 | July 20, 2022 | July 11, 2022 | 9d | LA-RICS UASI 19 C-136500 | $1,634,017 |
| 10 | July 20, 2022 | July 11, 2022 | 9d | LA-RICS UASI 19 C-136500 | $638,609 |
| 11 | July 20, 2022 | July 11, 2022 | 9d | LA-RICS UASI 19 C-136500 | $491,105 |
| 12 | July 20, 2022 | July 11, 2022 | 9d | LA-RICS UASI 19 C-136500 | $363,997 |
| 13 | July 20, 2022 | July 11, 2022 | 9d | LA-RICS UASI 19 C-136500 | $32,001 |
| 14 | July 20, 2022 | July 11, 2022 | 9d | LA-RICS UASI 19 C-136500 | $18,431 |
| 15 | August 8, 2022 | July 25, 2022 | 14d | LA-RICS UASI 19 C-136500 | $2,669,561 |
| 16 | August 8, 2022 | July 25, 2022 | 14d | LA-RICS UASI 19 C-136500 | $2,606,162 |
| 17 | August 8, 2022 | July 25, 2022 | 14d | LA-RICS UASI 19 C-136500 | $1,189,407 |
| 18 | August 8, 2022 | July 25, 2022 | 14d | LA-RICS UASI 19 C-136500 | $187,137 |
| 19 | August 9, 2022 | July 25, 2022 | 15d | LA-RICS UASI 19 C-136500 | $389,924 |
| 20 | August 9, 2022 | July 25, 2022 | 15d | LA-RICS UASI 19 C-136500 | $366,796 |
| 21 | August 9, 2022 | July 25, 2022 | 15d | LA-RICS UASI 19 C-136500 | $260,495 |
| 22 | August 9, 2022 | July 25, 2022 | 15d | LA-RICS UASI 19 C-136500 | $221,847 |
| 23 | August 9, 2022 | July 25, 2022 | 15d | LA-RICS UASI 19 C-136500 | $373 |
| 24 | October 19, 2022 | October 7, 2022 | 12d | LA-RICS UASI 19 C-136500 | $3,841,766 |
| 25 | October 19, 2022 | October 7, 2022 | 12d | LA-RICS UASI 19 C-136500 | $652,135 |
| 26 | October 19, 2022 | October 7, 2022 | 12d | LA-RICS UASI 19 C-136500 | $561,396 |
| 27 | October 19, 2022 | October 7, 2022 | 12d | LA-RICS UASI 19 C-136500 | $500,702 |
| 28 | October 19, 2022 | October 7, 2022 | 12d | LA-RICS UASI 19 C-136500 | $415,204 |
| 29 | December 23, 2022 | December 12, 2022 | 11d | LA-RICS UASI 19 C-136500 | $11,546,865 |
| 30 | December 23, 2022 | December 12, 2022 | 11d | LA-RICS UASI 19 C-136500 | $475,369 |
| 31 | December 23, 2022 | December 12, 2022 | 11d | LA-RICS UASI 19 C-136500 | $266,805 |
| 32 | December 23, 2022 | December 12, 2022 | 11d | LA-RICS UASI 19 C-136500 | $114,250 |
| 33 | December 23, 2022 | December 12, 2022 | 11d | LA-RICS UASI 19 C-136500 | $86,027 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.