What has the City paid on purchase order SC40CO24143069K?

$4.98M paid to Efs West across 21 payments from August 3, 2023 to March 11, 2025, charged to General Services / New 7th Street Body Shop (Phase II).

What it was for

New 7th Street Body Shop (Phase II)

Budget line.

Order description, as published:

TO ENCUM. $4,981,433.99 FOR CONSTR. 7TH ST NEW BODY SHOP

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated July 6, 2023.

Paid from

MICLA Lease Rev Com Paper Ntes

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: General Services

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 3, 2023June 2, 202362dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$673,930
2August 15, 2023August 1, 202314dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$298,300
3October 5, 2023September 5, 202330dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$176,225
4October 31, 2023October 2, 202329dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$186,675
5January 31, 2024November 6, 202386dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$186,675
6February 20, 2024December 4, 202378dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$224,371
7April 9, 2024March 18, 202422dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$179,313
8April 9, 2024March 18, 202422dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$150,575
9April 9, 2024March 8, 202432dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$140,125
10June 21, 2024June 3, 202418dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$199,240
11June 21, 2024June 3, 202418dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$152,735
12June 21, 2024April 12, 202470dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$112,760
13June 21, 2024May 8, 202444dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$99,750
14August 8, 2024July 30, 20249dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$244,047
15August 30, 2024August 20, 202410dTO PAY FOR 7TH ST. BODY SHOP CO#143069$36,813
16September 12, 2024September 1, 202411dTO PAY FOR 7TH ST. BODY SHOP CO#143069$313,500
17December 11, 2024November 6, 202435dTO PAY FOR 7TH ST. BODY SHOP CO#143069$369,075
18December 11, 2024October 1, 202471dTO PAY FOR 7TH ST. BODY SHOP CO#143069$116,655
19February 19, 2025February 5, 202514dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$471,305
20February 19, 2025February 5, 202514dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$467,377
21March 11, 2025February 13, 202526dTO PAY FOR CONSTRUCTION OF 7TH ST. BODY SHOP CO#143069$181,990

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.