SpendingContractsPurchase order
What has the City paid on purchase order SC40CO24134068M?
$1.24M paid to United Riggers/Erectors Inc across 28 payments from December 5, 2023 to November 26, 2025, charged to General Services / Construction Materials.
What it was for
Construction Materials
Budget line.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
General Fund
discretionary tax dollars — this competes with police, fire, parks and everything else.
Department: General Services
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | December 5, 2023 | November 6, 2023 | 29d | NTP#2931-4 WO#H1350005 ELEPHANT & GIRAFFE EXHIBIT/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $25,000 |
| 2 | December 5, 2023 | November 7, 2023 | 28d | NTP 2992 WO H3000100 CNC CD14 LINCOLN HEIGHTS FIELD OFFICE / TI (RIGGING & TRANSPORTATION) | $5,728 |
| 3 | February 9, 2024 | January 2, 2024 | 38d | NTP#2931-5 WO#H1350006 ZOO ELEPHANT & GIRAFFE EXHIBIT/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $44,479 |
| 4 | February 22, 2024 | February 13, 2024 | 9d | NTP 2931-4 WO H1350005 ZOO ELEPHANT & GIRAFFE EXHIBIT/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $33,880 |
| 5 | March 1, 2024 | February 21, 2024 | 9d | NTP 3037 WO H9140100 BSS 2484 E. OLYMPIC BL/CANOPY (RIGGING & TRANSPORTATION) | $12,092 |
| 6 | March 1, 2024 | February 21, 2024 | 9d | NTP 3053 WO H5870109 GSD BMDCHS/PLANTER & DECK WATERPROOFING (RIGGING & TRANSPORTATION) | $8,890 |
| 7 | March 6, 2024 | February 21, 2024 | 14d | NTP 3038 WO H0550100 BSS ASPHALT PLANT I/IMPROVEMENTS (RIGGING & TRANSPORTATION) | $25,529 |
| 8 | April 8, 2024 | March 21, 2024 | 18d | NTP#3021 WO#D4280300 DOT VARIOUS ATSAC COMM HUBS/REHAB (RIGGING & TRANSPORTATION) | $7,049 |
| 9 | April 9, 2024 | April 3, 2024 | 6d | NTP#3038 WO#H0550100 BSS ASPHALT PLANT I/IMPROVEMENTS (RIGGING & TRANSPORTATION) | $32,453 |
| 10 | April 22, 2024 | April 3, 2024 | 19d | NTP#3037 WO#H9140100 | $20,712 |
| 11 | April 23, 2024 | April 16, 2024 | 7d | NTP 2931-8 WO H1350009 ZOO ELEPHANT & GIRAFFE EXHIBIT/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $26,618 |
| 12 | April 23, 2024 | April 16, 2024 | 7d | NTP 2931-6 WO H1350007 ZOO ELEPHANT & GIRAFFE EXHIBIT/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $25,484 |
| 13 | April 24, 2024 | April 16, 2024 | 8d | NTP 2931-3 WO H1350004 ZOO ELEPHANT & GIRAFFE EXHIBIT/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $157,997 |
| 14 | April 25, 2024 | April 16, 2024 | 9d | NTP 2931-4 WO H1350005 ZOO ELEPHANT & GIRAFFE EXHIBIT/SHADES STRUCTURE (RIGGING & TRANSPORTATION) | $39,087 |
| 15 | May 15, 2024 | April 15, 2024 | 30d | NTP#2931-7 WO#H1350008 ZOO ELEPHANT & GIRAFFE EXHIB/SHADE STRUCTURE (RIGGING & TRANSPORTATION) | $3,060 |
| 16 | June 6, 2024 | May 29, 2024 | 8d | NTP 3079 WO H4500100 BOE SAN PEDRO CH PLAZA/RENOV (STRUCTURAL STEEL) | $54,684 |
| 17 | June 14, 2024 | June 11, 2024 | 3d | NTP 3038 WO H0550100 BSS ASPHALT PLANT I/IPMROVEMENTS (RIGGING & TRANSPORTATION) INV# 52872 | $9,900 |
| 18 | June 20, 2024 | June 10, 2024 | 10d | NTP#3037 WO#H9140100 BSS 2484 E. OLYMPIC BL/ CANOPY (RIGGING & TRANSPORTATION) | $9,900 |
| 19 | August 15, 2024 | August 6, 2024 | 9d | NTP 3037 WO H9140100 BSS 2484 E. OLYMPIC BL / CANOPY (RIGGING & TRANSPORTATION) | $37,178 |
| 20 | August 20, 2024 | August 6, 2024 | 14d | NTP 3038 WO H0550100 BSS ASPHALT PLANT I / IMPROVEMENTS | $58,060 |
| 21 | September 5, 2024 | August 20, 2024 | 16d | NTP 4020 WO D1970100 BOE BARNSDALL PARK RESIDENCE A | $7,158 |
| 22 | October 24, 2024 | October 3, 2024 | 21d | NTP 3037 WO H9140100 BSS 2484 E. OLYMPIC BL / CANOPY | $3,863 |
| 23 | December 9, 2024 | November 20, 2024 | 19d | NTP#3038 WO#H0550100 BSS ASPHALT PLANT I/IMPROVEMENTS (RIGGING AND TRANSPORTATION) | $16,427 |
| 24 | April 11, 2025 | April 1, 2025 | 10d | NTP 3079 WO H4500100 BOE SAN PEDRO CH PLAZA/RENOV | $59,400 |
| 25 | May 27, 2025 | May 9, 2025 | 18d | NTP 3079 WO H4500100 BOE SAN PEDRO CH PLAZA/RENOV | $248,173 |
| 26 | July 25, 2025 | June 26, 2025 | 29d | NTP#3079 WO#H4500100 BOE SAN PEDRO CH PLAZA/RENOV (STRUCTURAL STEEL) | $29,719 |
| 27 | August 6, 2025 | July 21, 2025 | 16d | NTP 3079 WO H4500100 BOE SAN PEDRO CH PLAZA/RENOV | $176,660 |
| 28 | November 26, 2025 | November 19, 2025 | 7d | NTP 3079 WO H4500100 BOE SAN PEDRO CH PLAZA/RENOV | $65,130 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.