SpendingContractsPurchase order
What has the City paid on purchase order SC21CO26202570Y?
$2.24M paid to Jenesse Center, Inc. across 52 payments from September 22, 2025 to September 4, 2026, charged to Los Angeles Housing / Contractual Services.
What it was for
Contractual Services
Budget line carrying the most money, of 4 this order is charged to.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Home-Arp Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Los Angeles Housing
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | September 22, 2025 | September 18, 2025 | 4d | 100SSPH FY26 | $29,949 |
| 2 | September 22, 2025 | September 18, 2025 | 4d | 65G SURVIVORS FIRST FHC2 | $21,025 |
| 3 | September 24, 2025 | September 18, 2025 | 6d | F4240001 FY26 | $140,042 |
| 4 | September 24, 2025 | September 18, 2025 | 6d | F4240001 FY26 | $140,042 |
| 5 | September 30, 2025 | September 18, 2025 | 12d | 65M SURVIVORS FIRST HOME-ARP | $21,025 |
| 6 | November 5, 2025 | October 28, 2025 | 8d | F4240001 FY26 | $61,578 |
| 7 | November 5, 2025 | October 28, 2025 | 8d | F4240001 FY26 | $61,578 |
| 8 | November 5, 2025 | October 28, 2025 | 8d | 100SSPH FY26 | $21,768 |
| 9 | November 5, 2025 | October 28, 2025 | 8d | 65G SURVIVORS FIRST FHC2 | $10,533 |
| 10 | November 13, 2025 | October 28, 2025 | 16d | 65M SURVIVORS FIRST HOME-ARP | $10,533 |
| 11 | December 3, 2025 | November 25, 2025 | 8d | F4240001 FY26 | $63,508 |
| 12 | December 3, 2025 | November 25, 2025 | 8d | 100SSPH FY26 | $37,963 |
| 13 | December 3, 2025 | November 25, 2025 | 8d | 100SSPH FY26 | $26,305 |
| 14 | December 3, 2025 | November 25, 2025 | 8d | F4240001 FY26 | $25,545 |
| 15 | December 3, 2025 | November 25, 2025 | 8d | 65G SURVIVORS FIRST FHC2 | $11,866 |
| 16 | December 3, 2025 | November 25, 2025 | 8d | 65M SURVIVORS FIRST HOME-ARP | $11,866 |
| 17 | February 4, 2026 | January 23, 2026 | 12d | 202570-JENESSE SS NOV-DEC'25 | $121,079 |
| 18 | February 4, 2026 | January 23, 2026 | 12d | 202570-JENESSE SS NOV-DEC'25 | $121,079 |
| 19 | February 4, 2026 | January 23, 2026 | 12d | 202570-JENESSE SS NOV-DEC'25 | $46,991 |
| 20 | February 4, 2026 | January 23, 2026 | 12d | 202570-JENESSE SS NOV-DEC'25 | $31,457 |
| 21 | February 23, 2026 | January 23, 2026 | 31d | 202570-JENESSE SS NOV-DEC'25 | $23,705 |
| 22 | March 9, 2026 | March 5, 2026 | 4d | 65G SURVIVORS FIRST FHC2 | $16,799 |
| 23 | March 9, 2026 | March 5, 2026 | 4d | F4240001 FY26 | $8,643 |
| 24 | March 11, 2026 | March 5, 2026 | 6d | 202570-JENESSE SS JAN'26 | $75,029 |
| 25 | March 11, 2026 | March 5, 2026 | 6d | 202570-JENESSE SS JAN'26 | $55,818 |
| 26 | March 11, 2026 | March 5, 2026 | 6d | 202570-JENESSE SS JAN'26 | $183 |
| 27 | March 16, 2026 | March 5, 2026 | 11d | 65M SURVIVORS FIRST HOME-ARP | $16,515 |
| 28 | March 27, 2026 | March 25, 2026 | 2d | 65G SURVIVORS FIRST FHC2 | $16,862 |
| 29 | March 31, 2026 | March 25, 2026 | 6d | 100SSPH FY26 | $53,018 |
| 30 | March 31, 2026 | March 25, 2026 | 6d | 100SSPH FY26 | $53,016 |
| 31 | March 31, 2026 | March 25, 2026 | 6d | 100SSPH FY26 | $27,516 |
| 32 | April 2, 2026 | March 25, 2026 | 8d | 65M SURVIVORS FIRST HOME-ARP | $11,862 |
| 33 | April 21, 2026 | April 16, 2026 | 5d | 65G SURVIVORS FIRST FHC2 | $15,973 |
| 34 | April 22, 2026 | April 16, 2026 | 6d | 100SSPH FY26 | $50,865 |
| 35 | April 22, 2026 | April 16, 2026 | 6d | 100SSPH FY26 | $50,864 |
| 36 | April 22, 2026 | April 16, 2026 | 6d | 100SSPH FY26 | $26,883 |
| 37 | May 1, 2026 | April 16, 2026 | 15d | 65M SURVIVORS FIRST HOME-ARP | $14,353 |
| 38 | July 17, 2026 | June 25, 2026 | 22d | 202570-JENESSE SS APR-MAY'26 | $57,453 |
| 39 | July 20, 2026 | June 25, 2026 | 25d | 202570-JENESSE SS APR-MAY'26 | $147,348 |
| 40 | July 20, 2026 | June 25, 2026 | 25d | 202570-JENESSE SS APR-MAY'26 | $100,364 |
| 41 | July 20, 2026 | June 25, 2026 | 25d | 202570-JENESSE SS APR-MAY'26 | $44,438 |
| 42 | July 29, 2026 | July 20, 2026 | 9d | 202570-JENESSE SS APR-MAY'26 | $42,045 |
| 43 | August 20, 2026 | August 5, 2026 | 15d | 202570-JENESSE SS JUNE'26 | $74,505 |
| 44 | August 20, 2026 | August 5, 2026 | 15d | 202570-JENESSE SS JUNE'26 | $38,971 |
| 45 | August 20, 2026 | August 5, 2026 | 15d | 202570-JENESSE SS JUNE'26 | $38,560 |
| 46 | August 20, 2026 | August 5, 2026 | 15d | 202570-JENESSE SS JUNE'26 | $7,306 |
| 47 | August 25, 2026 | August 21, 2026 | 4d | 202570-JENESSE SS JUNE'26 C/O | $19,214 |
| 48 | August 25, 2026 | August 21, 2026 | 4d | 202570-JENESSE SS JUNE'26 C/O | $10,028 |
| 49 | August 25, 2026 | August 21, 2026 | 4d | 202570-JENESSE SS JUNE'26 C/O | $9,609 |
| 50 | August 25, 2026 | August 21, 2026 | 4d | 202570-JENESSE SS JUNE'26 C/O | $6,342 |
| 51 | September 2, 2026 | August 5, 2026 | 28d | 202570-JENESSE SS JUNE'26 | $104,592 |
| 52 | September 4, 2026 | August 21, 2026 | 14d | 202570-JENESSE SS JUNE'26 C/O | $6,320 |
Download this table: ·