SpendingContractsPurchase order
What has the City paid on purchase order SC10CO26202278K?
$4.01M paid to Ford E C Inc across 12 payments from October 2, 2025 to August 31, 2026, charged to City Administrative Officer / CD 2 7724 Van Nuy Blvd THV.
What it was for
CD 2 7724 Van Nuy Blvd THV
Budget line.
Order description, as published:
ENC. $3,971,100 PER NTP 1 DTD 7/18/25
Approval records
- Contract C-202278Award recorded in the City's procurement portal; see below.
Order dated September 18, 2025.
Paid from
Emergency Stabilization Beds Grant
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: City Administrative Officer
Awarded and paid so far
The City's procurement portal, RAMP, records contract C-202278 (the number embedded in this order's number, SC10CO26202278K) as awarded to Ford E.C. Inc. for $4.0M (prequalified solicitation), effective July 16, 2025. This order has paid $4.0M, 101% of that figure.
The award amount and dates are as entered in RAMP; later amendments that change a contract's ceiling or term are not always reflected there, and a contract can be paid through orders not shown on this page. RAMP title: “CD 2 Tiny Home Village Van Nuys Metrolink”. See the award on RAMP
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | October 2, 2025 | September 18, 2025 | 14d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $490,416 |
| 2 | October 2, 2025 | September 2, 2025 | 30d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $364,768 |
| 3 | October 30, 2025 | October 20, 2025 | 10d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $732,930 |
| 4 | January 12, 2026 | November 24, 2025 | 49d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $513,345 |
| 5 | February 26, 2026 | December 19, 2025 | 69d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $154,782 |
| 6 | March 3, 2026 | January 21, 2026 | 41d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $94,998 |
| 7 | March 31, 2026 | February 23, 2026 | 36d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $922,357 |
| 8 | April 21, 2026 | March 23, 2026 | 29d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $104,228 |
| 9 | June 5, 2026 | May 7, 2026 | 29d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $255,829 |
| 10 | June 12, 2026 | May 13, 2026 | 30d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $150,123 |
| 11 | June 12, 2026 | May 22, 2026 | 21d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $50,339 |
| 12 | August 31, 2026 | July 28, 2026 | 34d | CD 2 TINY HOME VILLAGE - VAN NUYS METROLINK | $178,125 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. Award from RAMP Opportunity Awards (h8mw-iegk), matched on the contract number embedded in this order's number and on the vendor's name. The City's biggest contracts · The checkbook.