SpendingContractsPurchase order

What has the City paid on purchase order SC08MSACO16125828M?

$304K paid to 6 different vendors (the largest, Corporate Contractors Inc, received $122.8K) across 14 payments from July 21, 2017 to August 16, 2017, charged to Building and Safety / Alterations and Improvements.

A blanket order, not one firm's contract

6 different vendors draw against this purchase order, so the $304K above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

What it was for

Alterations and Improvements

Budget line.

Order description, as published:

PROJECT MGMT SVCS FOR DESIGN/CONSTRUCTION

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated July 1, 2017.

Paid from

Building & Safety Permit Enterpris

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Building and Safety

Paid to

Corporate Contractors Inc$123K · 3 payments
Unisource Solutions Inc$88K · 1 payment
M3 Office Inc$52K · 3 payments
Ex Novo Inc$30K · 4 payments
S.a.m. Moving Inc$8K · 1 payment

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1July 21, 2017July 17, 20174dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$87,948
2July 25, 2017July 18, 20177dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$43,002
3July 25, 2017July 17, 20178dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$11,337
4July 25, 2017July 17, 20178dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$9,181
5July 25, 2017July 18, 20177dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$6,389
6July 25, 2017July 17, 20178dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$2,852
7July 25, 2017July 17, 20178dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$2,299
8July 25, 2017July 13, 201712dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$2,066
9July 25, 2017July 17, 20178dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$595
10July 26, 2017July 17, 20179dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$116,613
11July 26, 2017July 17, 20179dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$3,152
12July 26, 2017July 13, 201713dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$3,069
13August 3, 2017July 14, 201720dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$8,252
14August 16, 2017August 15, 20171dPROJECT MGMT SVCS FOR DESIGN/ CONSTRUCTION AT 201 N. FIGUEROA ST$6,923

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.