SpendingContractsPurchase order

What has the City paid on purchase order SC08CO24137732M?

$775K paid to 8 different vendors (the largest, Corporate Contractors Inc, received $591.8K) across 32 payments from August 4, 2023 to February 21, 2024, charged to Building and Safety / Alterations and Improvements.

A blanket order, not one firm's contract

8 different vendors draw against this purchase order, so the $775K above is the whole order, not the spend of whichever vendor you arrived from. The City uses these for standing arrangements like outside counsel, library materials and expert witnesses. Per-vendor amounts are below.

What it was for

Alterations and Improvements

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Paid from

Building & Safety Permit Enterpris

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Building and Safety

Paid to

Corporate Contractors Inc$592K · 9 payments
M3 Office Inc$113K · 5 payments
Cbre Inc$22K · 3 payments
Ex Novo Inc$20K · 8 payments
Syska Hennessy Group Inc$19K · 1 payment
Mover Services Inc$7K · 2 payments
RD Systems Inc$495 · 1 payment

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1August 4, 2023July 26, 20239dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$116,883
2August 4, 2023July 24, 202311dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$96,617
3September 12, 2023September 6, 20236dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$280
4September 28, 2023September 25, 20233dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$495
5October 2, 2023September 21, 202311dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$142,068
6October 5, 2023October 2, 20233dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$1,947
7October 5, 2023October 2, 20233dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$608
8October 5, 2023October 3, 20232dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$595
9October 12, 2023October 10, 20232dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$43,961
10October 12, 2023October 10, 20232dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$4,229
11October 24, 2023October 12, 202312dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$73,551
12October 24, 2023October 16, 20238dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$62,908
13October 24, 2023October 18, 20236dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$19,681
14October 24, 2023October 20, 20234dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$2,237
15October 24, 2023October 17, 20237dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$1,430
16October 31, 2023October 27, 20234dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$4,994
17November 8, 2023November 2, 20236dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$19,400
18November 8, 2023November 2, 20236dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$6,202
19November 14, 2023November 14, 20230dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$43,961
20November 16, 2023November 14, 20232dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$10,072
21December 5, 2023December 4, 20231dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$1,250
22December 29, 2023December 21, 20238dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$324
23January 5, 2024December 28, 20238dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$1,868
24January 11, 2024January 4, 20247dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$85,650
25January 11, 2024December 29, 202313dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$13,443
26January 30, 2024January 19, 202411dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$2,280
27January 30, 2024January 19, 202411dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$1,154
28January 30, 2024January 18, 202412dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$1,119
29January 30, 2024January 23, 20247dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$249
30February 7, 2024January 29, 20249dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$7,488
31February 7, 2024January 29, 20249dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$802
32February 21, 2024February 15, 20246dTO PROVIDE PROJECT MANAGEMENT SERVICES FOR THE DESIGN AND CONSTRUCTION OF OFFICE SPACES$6,778

Download this table: ·

Draw-down shape

Sources