SpendingContractsPurchase order
What has the City paid on purchase order SC08CO20131051M?
$97K paid to Clay Reed across 60 payments from August 26, 2019 to March 3, 2021, charged to Building and Safety / Expenditure.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Repair & Demolition
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Building and Safety
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | August 26, 2019 | July 29, 2019 | 28d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $11,162 |
| 2 | August 26, 2019 | August 13, 2019 | 13d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $4,690 |
| 3 | August 26, 2019 | August 13, 2019 | 13d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $3,356 |
| 4 | August 26, 2019 | August 13, 2019 | 13d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $2,397 |
| 5 | August 26, 2019 | August 13, 2019 | 13d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $1,958 |
| 6 | August 26, 2019 | August 13, 2019 | 13d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $991 |
| 7 | September 4, 2019 | August 26, 2019 | 9d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $2,725 |
| 8 | September 5, 2019 | August 13, 2019 | 23d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $7,726 |
| 9 | September 5, 2019 | August 13, 2019 | 23d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $2,021 |
| 10 | September 23, 2019 | September 12, 2019 | 11d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $671 |
| 11 | September 23, 2019 | September 12, 2019 | 11d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $511 |
| 12 | October 24, 2019 | October 17, 2019 | 7d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $1,015 |
| 13 | October 30, 2019 | October 23, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,334 |
| 14 | October 30, 2019 | October 23, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $687 |
| 15 | October 30, 2019 | October 23, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $487 |
| 16 | October 30, 2019 | October 23, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 17 | October 30, 2019 | October 23, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 18 | November 6, 2019 | November 4, 2019 | 2d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $3,524 |
| 19 | November 6, 2019 | November 4, 2019 | 2d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $368 |
| 20 | December 3, 2019 | November 26, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $3,468 |
| 21 | December 3, 2019 | November 26, 2019 | 7d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $288 |
| 22 | December 3, 2019 | November 26, 2019 | 7d | ENCUMBER CLAY REED DBA AAXIS CONSTRUCTION | $256 |
| 23 | December 3, 2019 | November 26, 2019 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $224 |
| 24 | March 24, 2020 | March 17, 2020 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $6,168 |
| 25 | March 24, 2020 | March 17, 2020 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $4,554 |
| 26 | March 24, 2020 | March 17, 2020 | 7d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,438 |
| 27 | March 24, 2020 | March 16, 2020 | 8d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $407 |
| 28 | April 14, 2020 | March 17, 2020 | 28d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $3,100 |
| 29 | April 14, 2020 | March 17, 2020 | 28d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $2,828 |
| 30 | April 14, 2020 | April 3, 2020 | 11d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $2,749 |
| 31 | April 14, 2020 | April 3, 2020 | 11d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,342 |
| 32 | April 14, 2020 | April 3, 2020 | 11d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,115 |
| 33 | April 14, 2020 | April 3, 2020 | 11d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $879 |
| 34 | April 14, 2020 | March 17, 2020 | 28d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $783 |
| 35 | April 14, 2020 | March 17, 2020 | 28d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $330 |
| 36 | April 14, 2020 | April 2, 2020 | 12d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 37 | June 22, 2020 | June 5, 2020 | 17d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,774 |
| 38 | June 22, 2020 | May 26, 2020 | 27d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,262 |
| 39 | June 22, 2020 | May 26, 2020 | 27d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $991 |
| 40 | June 22, 2020 | June 5, 2020 | 17d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $671 |
| 41 | June 22, 2020 | June 5, 2020 | 17d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 42 | September 24, 2020 | September 14, 2020 | 10d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,774 |
| 43 | September 28, 2020 | September 14, 2020 | 14d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,622 |
| 44 | September 28, 2020 | September 14, 2020 | 14d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,422 |
| 45 | September 28, 2020 | September 16, 2020 | 12d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,366 |
| 46 | September 28, 2020 | September 14, 2020 | 14d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $799 |
| 47 | September 28, 2020 | September 14, 2020 | 14d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $479 |
| 48 | September 28, 2020 | September 14, 2020 | 14d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 49 | December 4, 2020 | November 10, 2020 | 24d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $2,565 |
| 50 | December 4, 2020 | November 10, 2020 | 24d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $2,141 |
| 51 | December 4, 2020 | November 6, 2020 | 28d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $639 |
| 52 | December 4, 2020 | November 9, 2020 | 25d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $240 |
| 53 | December 4, 2020 | November 9, 2020 | 25d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 54 | December 4, 2020 | November 9, 2020 | 25d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 55 | December 4, 2020 | November 9, 2020 | 25d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
| 56 | January 8, 2021 | December 10, 2020 | 29d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $1,566 |
| 57 | February 25, 2021 | February 12, 2021 | 13d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $256 |
| 58 | February 25, 2021 | February 11, 2021 | 14d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $240 |
| 59 | March 3, 2021 | February 22, 2021 | 9d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $232 |
| 60 | March 3, 2021 | February 22, 2021 | 9d | TO ENCUMBER FUNDS - CLAY REED DBA AAXIS CONSTRUCTION | $200 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.