What has the City paid on purchase order GAEAE86AE23000005M?
$4K paid to Department of General Services across 12 payments from September 12, 2022 to August 14, 2023, charged to Public Works - Street Services / Utilities Expense Private Company.
What it was for
Utilities Expense Private CompanyBudget line.
Order description, as published:
ENCUMBER $4,574.64 FOR SERVICE FEES FOR USE OF GAS LINES
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated July 7, 2022.
Paid from
General Fund
discretionary tax dollars — this competes with police, fire, parks and everything else.
Department: Public Works - Street Services
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | September 12, 2022 | August 29, 2022 | 14d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR JULY 2022 | $363 |
| 2 | October 18, 2022 | September 28, 2022 | 20d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR AUG 2022 | $363 |
| 3 | November 22, 2022 | October 27, 2022 | 26d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR SEPT 2022 | $363 |
| 4 | December 21, 2022 | November 29, 2022 | 22d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR OCT 2022 | $363 |
| 5 | February 7, 2023 | February 3, 2023 | 4d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR NOV 2022 | $363 |
| 6 | February 17, 2023 | January 28, 2023 | 20d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR DEC 2022 | $363 |
| 7 | March 20, 2023 | February 27, 2023 | 21d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR JAN 2023 | $363 |
| 8 | April 17, 2023 | March 29, 2023 | 19d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR FEB 2023 | $363 |
| 9 | May 22, 2023 | April 27, 2023 | 25d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR MAR 2023 | $363 |
| 10 | July 10, 2023 | May 26, 2023 | 45d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR APRIL 2023 | $363 |
| 11 | July 10, 2023 | June 28, 2023 | 12d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR MAY 2023 | $363 |
| 12 | August 14, 2023 | July 28, 2023 | 17d | USE OF GAS LINES TO OPERATE HEATER AND DRYER EQUIPMENT AT BSS' ASPHALT PLANTS FOR JUNE 2023 | $363 |
Download this table: ·