SpendingContractsPurchase order
What has the City paid on purchase order CPO94250000479760?
$239K paid to Axiom Group across 25 payments from August 7, 2025 to December 8, 2025, charged to Transportation / Speed Hump Program.
What it was for
Speed Hump ProgramBudget line.
Order description, as published:
SMUF # 39857 - ERIC MAYA 213 216-7605
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated May 13, 2025.
Paid from
Measure M Local Return Special Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Transportation
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | August 7, 2025 | July 11, 2025 | 27d | ASPHALT, SPEED HUMP, TYPE I | $67,536 |
| 2 | August 7, 2025 | July 11, 2025 | 27d | PERMITS, CLASS "A" CONSTRUCTION | $7,250 |
| 3 | August 7, 2025 | July 11, 2025 | 27d | CHEVRONS, THERMOPLASTIC | $4,350 |
| 4 | August 7, 2025 | July 11, 2025 | 27d | SIGN, ADVANCED WARNING BUMP SIGN, SIGN POSTS INCLS INSTALL | $2,610 |
| 5 | August 7, 2025 | July 11, 2025 | 27d | PAVEMENT MARKING, BUMP LEGEND, MATERIAL & INSTALLATION | $2,393 |
| 6 | August 7, 2025 | July 11, 2025 | 27d | SIGN, ADVANCED WARNING BUMP SIGN, INSTALLED TO STREET LIGHT | $870 |
| 7 | October 1, 2025 | August 18, 2025 | 44d | ASPHALT, SPEED HUMP, TYPE I | $70,128 |
| 8 | October 1, 2025 | August 18, 2025 | 44d | PERMITS, CLASS "A" CONSTRUCTION | $7,250 |
| 9 | October 1, 2025 | August 18, 2025 | 44d | CHEVRONS, THERMOPLASTIC | $4,350 |
| 10 | October 1, 2025 | August 18, 2025 | 44d | SIGN, ADVANCED WARNING BUMP SIGN, SIGN POSTS INCLS INSTALL | $3,915 |
| 11 | October 1, 2025 | August 18, 2025 | 44d | PAVEMENT MARKING, BUMP LEGEND, MATERIAL & INSTALLATION | $2,393 |
| 12 | October 1, 2025 | August 18, 2025 | 44d | SIGN, ADVANCED WARNING BUMP SIGN, INSTALLED TO STREET LIGHT | $218 |
| 13 | October 7, 2025 | August 26, 2025 | 42d | ASPHALT, SPEED HUMP, TYPE I | $18,432 |
| 14 | October 7, 2025 | August 26, 2025 | 42d | PERMITS, CLASS "A" CONSTRUCTION | $1,450 |
| 15 | October 7, 2025 | August 26, 2025 | 42d | CHEVRONS, THERMOPLASTIC | $1,160 |
| 16 | October 7, 2025 | August 26, 2025 | 42d | PAVEMENT MARKING, BUMP LEGEND, MATERIAL & INSTALLATION | $479 |
| 17 | October 7, 2025 | August 26, 2025 | 42d | SIGN, ADVANCED WARNING BUMP SIGN, SIGN POSTS INCLS INSTALL | $435 |
| 18 | October 7, 2025 | August 26, 2025 | 42d | SIGN, ADVANCED WARNING BUMP SIGN, INSTALLED TO STREET LIGHT | $218 |
| 19 | December 8, 2025 | October 31, 2025 | 38d | ASPHALT, SPEED HUMP, TYPE I | $29,952 |
| 20 | December 8, 2025 | October 31, 2025 | 38d | ASPHALT, SPEED HUMP, TYPE II | $6,264 |
| 21 | December 8, 2025 | October 31, 2025 | 38d | PERMITS, CLASS "A" CONSTRUCTION | $2,900 |
| 22 | December 8, 2025 | October 31, 2025 | 38d | CHEVRONS, THERMOPLASTIC | $2,030 |
| 23 | December 8, 2025 | October 31, 2025 | 38d | PAVEMENT MARKING, BUMP LEGEND, MATERIAL & INSTALLATION | $957 |
| 24 | December 8, 2025 | October 31, 2025 | 38d | SIGN, ADVANCED WARNING BUMP SIGN, INSTALLED TO STREET LIGHT | $653 |
| 25 | December 8, 2025 | October 31, 2025 | 38d | SIGN, ADVANCED WARNING BUMP SIGN, SIGN POSTS INCLS INSTALL | $435 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.