What has the City paid on purchase order CPO94230000423068?

$1.72M paid to All-Phase Electric Supply Co across 8 payments from December 21, 2022 to October 2, 2023, charged to Transportation / Atp 2 - Colorado Pedestrian Improvements.

What it was for

Atp 2 - Colorado Pedestrian Improvements

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated September 28, 2022.

Paid from

Transportation Grants Fund

restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.

Department: Transportation

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1December 21, 2022December 2, 202219d400W HPS LED EQUAL$20,460
2February 28, 2023February 3, 202325dCD953A POLE$58,792
3February 28, 2023February 3, 202325d4FT LUMINAIRE ARM$5,358
4May 15, 2023April 25, 202320dCLA-KA72-T-1-36"-SSG LUM ARM$309,804
5May 26, 2023May 16, 202310d-120:277-KPL10-SSG LUMINAIRE$722,037
6May 26, 2023May 16, 202310dCLA-KM96FC-SSG POLE$447,076
7October 2, 2023September 11, 202321dCLA-KM96FC-SSG POLE$129,155
8October 2, 2023September 11, 202321dCLA-KM96FC-SSG POLE BASE$29,805

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.