SpendingContractsPurchase order

What has the City paid on purchase order CPO84190000449830?

$15K paid to All-Phase Electric Supply Co across 2 payments on April 15, 2019, charged to Non-Departmental - Capital Improvement Expense Program / Street Lighting at Existing Pedestrian Crosswalks.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated January 10, 2019.

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: Non-Departmental - Capital Improvement Expense Program

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1April 15, 2019March 20, 201926d20W - 180 DEGREE LAMP$11,871
2April 15, 2019March 20, 201926d60W - 180 DEGREE LAMP$3,421

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.