SpendingContractsPurchase order
What has the City paid on purchase order CPO78250000428215?
$8K paid to Oracle America Inc across 80 payments from March 25, 2025 to December 15, 2025, charged to Non-Departmental - Appropriations to Special Purpose Fund / PW-Engineering Expense & Equip.
What it was for
PW-Engineering Expense & Equip
Budget line carrying the most money, of 2 this order is charged to.
Order description, as published:
COVERAGE DATES: 11/23/24-11/22/25
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated October 10, 2024.
Paid from
Sewer Capital Fund
Department: Non-Departmental - Appropriations to Special Purpose Fund
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 2 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 3 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 4 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 5 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 6 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 7 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 8 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 9 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 10 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 11 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 12 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 13 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 14 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 15 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 16 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 17 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 18 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 19 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 20 | March 25, 2025 | February 26, 2025 | 27d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 21 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 22 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 23 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 24 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 25 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 26 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 27 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 28 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 29 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 30 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 31 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 32 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 33 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 34 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 35 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 36 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 37 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 38 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 39 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 40 | June 10, 2025 | June 3, 2025 | 7d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 41 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 42 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 43 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 44 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 45 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 46 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 47 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 48 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 49 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 50 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 51 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 52 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 53 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 54 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 55 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 56 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 57 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 58 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 59 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 60 | September 17, 2025 | August 22, 2025 | 26d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 61 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 62 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 63 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 64 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 65 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 66 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 67 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 68 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 69 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 70 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 71 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 72 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 73 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 74 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 75 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 76 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 77 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P6 PROFESSIONAL PROJECT MANAGEMENT-APPLICATION USE | $167 |
| 78 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 79 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
| 80 | December 15, 2025 | November 25, 2025 | 20d | PRIMAVERA P3E/C PROJECT PLANNER PROFESSIONAL-CONCURRENT USER | $73 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.