$47K paid to KDC Inc., Dynalectric Company across 8 payments on November 27, 2018, charged to Non-Departmental / Vision Zero Corridor Projects - SB1.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
Road Maintenance and Rehabilitation Program Special Fund
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Non-Departmental
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | November 27, 2018 | June 15, 2018 | 165d | CONDUIT, 3" SCHEDULE 80 PVC (30" COVER) IN ASPHALT STREET, T | $18,645 |
| 2 | November 27, 2018 | June 15, 2018 | 165d | INSTALL FOUNDATIONS | $18,000 |
| 3 | November 27, 2018 | June 15, 2018 | 165d | INSTALL MISCELLANEOUS ITEMS RELATED TO PVC CONDUIT | $4,400 |
| 4 | November 27, 2018 | June 15, 2018 | 165d | SERVICE, REMOVAL & DISPOSAL OF EXISTING FOUNDATIONS | $2,130 |
| 5 | November 27, 2018 | June 15, 2018 | 165d | INSTALLATION, PULLBOX DURING REGULAR WORKING HOURS | $1,965 |
| 6 | November 27, 2018 | June 15, 2018 | 165d | PULLBOX, ELECTRICAL, FIBERCRETE, TYPE 2, MANUFACTURER: AMORC | $1,150 |
| 7 | November 27, 2018 | June 15, 2018 | 165d | INSTALLATION, PULLBOX DURING REGULAR WORKING HOURS | $705 |
| 8 | November 27, 2018 | June 15, 2018 | 165d | PULLBOX, ELECTRICAL, FIBERCRETE, TYPE 3. MANUFACTURER: AMORC | $460 |
Download this table: ·
Draw-down shape
Sources