SpendingContractsPurchase order

What has the City paid on purchase order CPO40240000446118?

$491K paid to Quality Fence Co Inc across 7 payments from September 13, 2024 to October 25, 2024, charged to General Services / Construction Materials.

What it was for

Construction Materials

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated December 14, 2023.

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: General Services

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1September 13, 2024August 21, 202423dLABOR, HOURLY RATE TO PROVIDE A TRACTOR DIGGER INCLUDING OPE$141,966
2September 13, 2024August 21, 202423dFENCE, 9 GAUGE, 6 FEET HIGH, "MERCHANT METALS"$28,619
3September 13, 2024August 21, 202423dEXTENSION ARMS ONLY, PRESSED STEEL FOR BARBED WIRE, "MERCHAN$22,895
4September 13, 2024August 21, 202423dCONCRETE FOOTING FOR LINE POSTS, 2 FEET DEEP BY 12" IN DIAME$20,033
5September 13, 2024August 21, 202423dFENCE CONSTRUCTION SERVICE$15,682
6September 13, 2024August 21, 202423dFENCE CONSTRUCTION SERVICE$15,682
7October 25, 2024October 1, 202424dLABOR, HOURLY RATE TO PROVIDE A 2 MAN CREW INCLUDING TRUCK A$246,074

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.