SpendingContractsPurchase order
What has the City paid on purchase order CPO40220000442478?
$3.34M paid to Haaker Equipment Co across 42 payments from April 27, 2023 to May 26, 2023, charged to General Services / GSD Replacement Fleet Equipment & Vehicles.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Order dated January 5, 2022.
Paid from
MICLA Lease Rev Com Paper Ntes
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: General Services
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | April 27, 2023 | April 10, 2023 | 17d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 2 | April 27, 2023 | April 10, 2023 | 17d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 3 | April 27, 2023 | April 10, 2023 | 17d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 4 | April 27, 2023 | April 10, 2023 | 17d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 5 | April 27, 2023 | April 10, 2023 | 17d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 6 | April 27, 2023 | April 10, 2023 | 17d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 7 | April 27, 2023 | April 10, 2023 | 17d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 8 | April 27, 2023 | April 10, 2023 | 17d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 9 | April 27, 2023 | April 10, 2023 | 17d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 10 | April 27, 2023 | April 10, 2023 | 17d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 11 | April 27, 2023 | April 10, 2023 | 17d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 12 | April 27, 2023 | April 10, 2023 | 17d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 13 | April 27, 2023 | April 10, 2023 | 17d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 14 | April 27, 2023 | April 10, 2023 | 17d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 15 | April 27, 2023 | April 10, 2023 | 17d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 16 | April 27, 2023 | April 10, 2023 | 17d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 17 | April 27, 2023 | April 10, 2023 | 17d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 18 | April 27, 2023 | April 10, 2023 | 17d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 19 | April 27, 2023 | April 10, 2023 | 17d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 20 | April 27, 2023 | April 10, 2023 | 17d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 21 | April 27, 2023 | April 10, 2023 | 17d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 22 | April 27, 2023 | April 10, 2023 | 17d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 23 | April 27, 2023 | April 10, 2023 | 17d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 24 | April 27, 2023 | April 10, 2023 | 17d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 25 | April 27, 2023 | April 10, 2023 | 17d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 26 | April 27, 2023 | April 10, 2023 | 17d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 27 | April 27, 2023 | April 10, 2023 | 17d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 28 | April 27, 2023 | April 10, 2023 | 17d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 29 | April 27, 2023 | April 10, 2023 | 17d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 30 | April 27, 2023 | April 10, 2023 | 17d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 31 | April 27, 2023 | April 10, 2023 | 17d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
| 32 | April 27, 2023 | April 10, 2023 | 17d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
| 33 | April 27, 2023 | April 10, 2023 | 17d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
| 34 | April 27, 2023 | April 10, 2023 | 17d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
| 35 | April 27, 2023 | April 10, 2023 | 17d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
| 36 | April 27, 2023 | April 10, 2023 | 17d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
| 37 | May 26, 2023 | May 18, 2023 | 8d | SWEEPER, STREET, ELGIN BROOM BEAR | $470,571 |
| 38 | May 26, 2023 | May 18, 2023 | 8d | OPTION D: ADDITIONAL PICK-UP BROOM CORE, AMERICAN ROTARY | $2,632 |
| 39 | May 26, 2023 | May 18, 2023 | 8d | OPTION E: ADDITIONAL GUTTER BROOM SEGMENTS, AMERICAN ROTARY | $1,386 |
| 40 | May 26, 2023 | May 18, 2023 | 8d | OPTION F: FACTORY DISC BRAKES, FREIGHTLINER | $1,040 |
| 41 | May 26, 2023 | May 18, 2023 | 8d | FREIGHTLINER PARTS/ SERVICE MANUALS | $1,040 |
| 42 | May 26, 2023 | May 18, 2023 | 8d | OPTION C: TELEVISION SAFETY BACKUP UNIT | $744 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.