What has the City paid on purchase order CPO40180000416271?

$142K paid to Best Contracting Services Inc across 23 payments on February 28, 2018, charged to Non-Departmental - Capital Improvement Expense Program / Citywide Roofing Repair.

What it was for

Citywide Roofing Repair

Budget line.

Approval records

No council file, contract number or payment authority appears in this order's checkbook records.

Order dated August 25, 2017.

Paid from

General Fund

discretionary tax dollars — this competes with police, fire, parks and everything else.

Department: Non-Departmental - Capital Improvement Expense Program

Every payment, in order

Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.

#PaidInvoicedLagReferenceAmount
1February 28, 2018February 5, 201823dMATERIAL: INSTALL SBS LIBERTY SELF ADHERING RUBEROID SYSTEM$24,581
2February 28, 2018February 5, 201823dLABOR: INSTALL SBS LIBERTY SELF ADHERING RUBEROID SYSTEM$11,250
3February 28, 2018February 5, 201823dREMOVE THIRD LAYER OF CAP SHEET ROOF APPROX. 15,300 SQ. FT$10,710
4February 28, 2018February 5, 201823dREMOVE FIRST LAYER OF INSULATION BOARD ROOF APPROX. 15,300$10,710
5February 28, 2018February 5, 201823dREMOVE SECOND LAYER OF CAP SHEET ROOF APPROX. 15,300 SQ. FT$10,710
6February 28, 2018February 5, 201823dMATERIAL: 2 INCH INSULATION BOARD$9,734
7February 28, 2018February 5, 201823dBUILDING SUPPORT SERVICES$7,800
8February 28, 2018February 5, 201823dLABOR: INSTALL 2 INCH INSULATION BOARD$7,473
9February 28, 2018February 5, 201823dLABOR: 2 INCH LEAD FLASHING$7,425
10February 28, 2018February 5, 201823dLABOR: INSTALL 1/4" DENS DECK BOARD$6,750
11February 28, 2018February 5, 201823dMATERIAL: DENS DECK BOARD 1/4"$6,293
12February 28, 2018February 5, 201823dEQUIPMENT (MAN LIFT)$5,250
13February 28, 2018February 5, 201823dREMOVE FIRST LAYER OF CAP SHEET ROOF APPROX. 15,300 SQ. FT.$4,500
14February 28, 2018February 5, 201823dMATERIAL: APP TORCH APPLIED ROOFING SYSTEM$3,835
15February 28, 2018February 5, 201823dLABOR: INSTALL REGLET COUNTER FLASHING$3,600
16February 28, 2018February 5, 201823dBUILDING SUPPORT SERVICES$3,250
17February 28, 2018February 5, 201823dLABOR: APP TORCH APPLIED ROOFING SYSTEM$2,970
18February 28, 2018February 5, 201823dMATERIAL: 2 INCH LEAD FLASHING$2,283
19February 28, 2018February 5, 201823dMATERIAL: INSTALL REGLET COUNTER FLASHING$983
20February 28, 2018February 5, 201823dLABOR: TPO SINGLE PLY TERMINATION BAR$864
21February 28, 2018February 5, 201823dMATERIAL: TPO SINGLE PLY TERMINATION BAR$649
22February 28, 2018February 5, 201823dLABOR: INSTALL 3"X3" METAL EDGING$336
23February 28, 2018February 5, 201823dMATERIAL: 3"X3" METAL EDGING$184

Download this table: ·

Draw-down shape

Sources

LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.