$4.76M paid to Pierce Manufacturing Inc across 100 payments from September 15, 2021 to April 26, 2022, charged to Fire / Fleet Replacement.
Approval records
No council file, contract number or payment authority appears in this order's checkbook records.
Paid from
MICLA Lease Rev Com Paper Ntes
restricted revenue (grants, fees or a dedicated tax) that can only be spent on this purpose — not general-fund tax dollars.
Department: Fire
Every payment, in order
Payment requests are numbered sequentially by the City, so the order here is the order they were approved. Several requests clearing on one day usually means invoices were held and released together.
| # | Paid | Invoiced | Lag | Reference | Amount |
|---|---|---|---|---|---|
| 1 | September 15, 2021 | August 25, 2021 | 21d | AERIAL LADDER TRUCK, 100' TRACTOR DRAWN PER SPECIFICATION FD | $1,134,810 |
| 2 | September 15, 2021 | August 18, 2021 | 28d | AERIAL LADDER TRUCK, 100' TRACTOR DRAWN PER SPECIFICATION FD | $1,134,810 |
| 3 | September 15, 2021 | August 25, 2021 | 21d | 43.3.1 SPECIFIED QUANTITIES | $12,286 |
| 4 | September 15, 2021 | August 18, 2021 | 28d | 43.3.1 SPECIFIED QUANTITIES | $12,286 |
| 5 | September 15, 2021 | August 18, 2021 | 28d | 43.3.4 SPECIFIED QUANTITIES | $9,549 |
| 6 | September 15, 2021 | August 25, 2021 | 21d | 43.3.4 SPECIFIED QUANTITIES | $9,549 |
| 7 | September 15, 2021 | August 25, 2021 | 21d | 43.3.3 SPECIFIED QUANTITIES | $8,123 |
| 8 | September 15, 2021 | August 18, 2021 | 28d | 43.3.3 SPECIFIED QUANTITIES | $8,123 |
| 9 | September 15, 2021 | August 25, 2021 | 21d | 43.3.2 SPECIFIED QUANTITIES | $6,486 |
| 10 | September 15, 2021 | August 18, 2021 | 28d | 43.3.2 SPECIFIED QUANTITIES | $6,486 |
| 11 | September 15, 2021 | August 18, 2021 | 28d | 43.3.7 SPECIFIED QUANTITIES | $4,568 |
| 12 | September 15, 2021 | August 25, 2021 | 21d | 43.3.7 SPECIFIED QUANTITIES | $4,568 |
| 13 | September 15, 2021 | August 18, 2021 | 28d | 43.3.6 SPECIFIED QUANTITIES | $3,874 |
| 14 | September 15, 2021 | August 25, 2021 | 21d | 43.3.6 SPECIFIED QUANTITIES | $3,874 |
| 15 | September 15, 2021 | August 25, 2021 | 21d | 43.3.5 SPECIFIED QUANTITIES | $3,195 |
| 16 | September 15, 2021 | August 18, 2021 | 28d | 43.3.5 SPECIFIED QUANTITIES | $3,195 |
| 17 | September 15, 2021 | August 18, 2021 | 28d | 43.3.9 SPECIFIED QUANTITIES | $2,752 |
| 18 | September 15, 2021 | August 25, 2021 | 21d | 43.3.9 SPECIFIED QUANTITIES | $2,752 |
| 19 | September 15, 2021 | August 25, 2021 | 21d | 43.3.8 SPECIFIED QUANTITIES | $1,733 |
| 20 | September 15, 2021 | August 18, 2021 | 28d | 43.3.8 SPECIFIED QUANTITIES | $1,733 |
| 21 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.6 SPECIFIED QUANTITIES | $447 |
| 22 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.6 SPECIFIED QUANTITIES | $447 |
| 23 | September 15, 2021 | August 25, 2021 | 21d | 43.2.1 SPECIFIED QUANTITIES | $425 |
| 24 | September 15, 2021 | August 18, 2021 | 28d | 43.2.1 SPECIFIED QUANTITIES | $425 |
| 25 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.3 SPECIFIED QUANTITIES | $397 |
| 26 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.3 SPECIFIED QUANTITIES | $397 |
| 27 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.1 SPECIFIED QUANTITIES | $314 |
| 28 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.1 SPECIFIED QUANTITIES | $314 |
| 29 | September 15, 2021 | August 18, 2021 | 28d | 43.1.5 SPECIFIED QUANTITIES | $284 |
| 30 | September 15, 2021 | August 25, 2021 | 21d | 43.1.5 SPECIFIED QUANTITIES | $284 |
| 31 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.5 SPECIFIED QUANTITIES | $263 |
| 32 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.5 SPECIFIED QUANTITIES | $263 |
| 33 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.2 SPECIFIED QUANTITIES | $230 |
| 34 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.2 SPECIFIED QUANTITIES | $230 |
| 35 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.4 SPECIFIED QUANTITIES | $222 |
| 36 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.4 SPECIFIED QUANTITIES | $222 |
| 37 | September 15, 2021 | August 18, 2021 | 28d | 43.1.2 SPECIFIED QUANTITIES | $171 |
| 38 | September 15, 2021 | August 25, 2021 | 21d | 43.1.2 SPECIFIED QUANTITIES | $171 |
| 39 | September 15, 2021 | August 25, 2021 | 21d | 43.1.4 SPECIFIED QUANTITIES | $169 |
| 40 | September 15, 2021 | August 18, 2021 | 28d | 43.1.4 SPECIFIED QUANTITIES | $169 |
| 41 | September 15, 2021 | August 18, 2021 | 28d | 43.1.6 SPECIFIED QUANTITIES | $143 |
| 42 | September 15, 2021 | August 25, 2021 | 21d | 43.1.6 SPECIFIED QUANTITIES | $143 |
| 43 | September 15, 2021 | August 18, 2021 | 28d | 43.1.3 SPECIFIED QUANTITIES | $108 |
| 44 | September 15, 2021 | August 25, 2021 | 21d | 43.1.3 SPECIFIED QUANTITIES | $108 |
| 45 | September 15, 2021 | August 18, 2021 | 28d | 43.1.7 SPECIFIED QUANTITIES | $93 |
| 46 | September 15, 2021 | August 25, 2021 | 21d | 43.1.7 SPECIFIED QUANTITIES | $93 |
| 47 | September 15, 2021 | August 18, 2021 | 28d | 43.1.1 SPECIFIED QUANTITIES | $85 |
| 48 | September 15, 2021 | August 25, 2021 | 21d | 43.1.1 SPECIFIED QUANTITIES | $85 |
| 49 | September 15, 2021 | August 18, 2021 | 28d | 43.1.8.7 SPECIFIED QUANTITIES | $71 |
| 50 | September 15, 2021 | August 25, 2021 | 21d | 43.1.8.7 SPECIFIED QUANTITIES | $71 |
| 51 | December 21, 2021 | November 24, 2021 | 27d | AERIAL LADDER TRUCK, 100' TRACTOR DRAWN PER SPECIFICATION FD | $1,134,810 |
| 52 | December 21, 2021 | November 24, 2021 | 27d | 43.3.1 SPECIFIED QUANTITIES | $12,286 |
| 53 | December 21, 2021 | November 24, 2021 | 27d | 43.3.4 SPECIFIED QUANTITIES | $9,549 |
| 54 | December 21, 2021 | November 24, 2021 | 27d | 43.3.3 SPECIFIED QUANTITIES | $8,123 |
| 55 | December 21, 2021 | November 24, 2021 | 27d | 43.3.2 SPECIFIED QUANTITIES | $6,486 |
| 56 | December 21, 2021 | November 24, 2021 | 27d | 43.3.7 SPECIFIED QUANTITIES | $4,568 |
| 57 | December 21, 2021 | November 24, 2021 | 27d | 43.3.6 SPECIFIED QUANTITIES | $3,874 |
| 58 | December 21, 2021 | November 24, 2021 | 27d | 43.3.5 SPECIFIED QUANTITIES | $3,195 |
| 59 | December 21, 2021 | November 24, 2021 | 27d | 43.3.9 SPECIFIED QUANTITIES | $2,752 |
| 60 | December 21, 2021 | November 24, 2021 | 27d | 43.3.8 SPECIFIED QUANTITIES | $1,733 |
| 61 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.6 SPECIFIED QUANTITIES | $447 |
| 62 | December 21, 2021 | November 24, 2021 | 27d | 43.2.1 SPECIFIED QUANTITIES | $425 |
| 63 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.3 SPECIFIED QUANTITIES | $397 |
| 64 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.1 SPECIFIED QUANTITIES | $314 |
| 65 | December 21, 2021 | November 24, 2021 | 27d | 43.1.5 SPECIFIED QUANTITIES | $284 |
| 66 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.5 SPECIFIED QUANTITIES | $263 |
| 67 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.2 SPECIFIED QUANTITIES | $230 |
| 68 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.4 SPECIFIED QUANTITIES | $222 |
| 69 | December 21, 2021 | November 24, 2021 | 27d | 43.1.2 SPECIFIED QUANTITIES | $171 |
| 70 | December 21, 2021 | November 24, 2021 | 27d | 43.1.4 SPECIFIED QUANTITIES | $169 |
| 71 | December 21, 2021 | November 24, 2021 | 27d | 43.1.6 SPECIFIED QUANTITIES | $143 |
| 72 | December 21, 2021 | November 24, 2021 | 27d | 43.1.3 SPECIFIED QUANTITIES | $108 |
| 73 | December 21, 2021 | November 24, 2021 | 27d | 43.1.7 SPECIFIED QUANTITIES | $93 |
| 74 | December 21, 2021 | November 24, 2021 | 27d | 43.1.1 SPECIFIED QUANTITIES | $85 |
| 75 | December 21, 2021 | November 24, 2021 | 27d | 43.1.8.7 SPECIFIED QUANTITIES | $71 |
| 76 | April 26, 2022 | April 13, 2022 | 13d | AERIAL LADDER TRUCK, 100' TRACTOR DRAWN PER SPECIFICATION FD | $1,134,810 |
| 77 | April 26, 2022 | April 13, 2022 | 13d | 43.3.1 SPECIFIED QUANTITIES | $12,286 |
| 78 | April 26, 2022 | April 13, 2022 | 13d | 43.3.4 SPECIFIED QUANTITIES | $9,549 |
| 79 | April 26, 2022 | April 13, 2022 | 13d | 43.3.3 SPECIFIED QUANTITIES | $8,123 |
| 80 | April 26, 2022 | April 13, 2022 | 13d | 43.3.2 SPECIFIED QUANTITIES | $6,486 |
| 81 | April 26, 2022 | April 13, 2022 | 13d | 43.3.7 SPECIFIED QUANTITIES | $4,568 |
| 82 | April 26, 2022 | April 13, 2022 | 13d | 43.3.6 SPECIFIED QUANTITIES | $3,874 |
| 83 | April 26, 2022 | April 13, 2022 | 13d | 43.3.5 SPECIFIED QUANTITIES | $3,195 |
| 84 | April 26, 2022 | April 13, 2022 | 13d | 43.3.9 SPECIFIED QUANTITIES | $2,752 |
| 85 | April 26, 2022 | April 13, 2022 | 13d | 43.3.8 SPECIFIED QUANTITIES | $1,733 |
| 86 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.6 SPECIFIED QUANTITIES | $447 |
| 87 | April 26, 2022 | April 13, 2022 | 13d | 43.2.1 SPECIFIED QUANTITIES | $425 |
| 88 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.3 SPECIFIED QUANTITIES | $397 |
| 89 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.1 SPECIFIED QUANTITIES | $314 |
| 90 | April 26, 2022 | April 13, 2022 | 13d | 43.1.5 SPECIFIED QUANTITIES | $284 |
| 91 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.5 SPECIFIED QUANTITIES | $263 |
| 92 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.2 SPECIFIED QUANTITIES | $230 |
| 93 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.4 SPECIFIED QUANTITIES | $222 |
| 94 | April 26, 2022 | April 13, 2022 | 13d | 43.1.2 SPECIFIED QUANTITIES | $171 |
| 95 | April 26, 2022 | April 13, 2022 | 13d | 43.1.4 SPECIFIED QUANTITIES | $169 |
| 96 | April 26, 2022 | April 13, 2022 | 13d | 43.1.6 SPECIFIED QUANTITIES | $143 |
| 97 | April 26, 2022 | April 13, 2022 | 13d | 43.1.3 SPECIFIED QUANTITIES | $108 |
| 98 | April 26, 2022 | April 13, 2022 | 13d | 43.1.7 SPECIFIED QUANTITIES | $93 |
| 99 | April 26, 2022 | April 13, 2022 | 13d | 43.1.1 SPECIFIED QUANTITIES | $85 |
| 100 | April 26, 2022 | April 13, 2022 | 13d | 43.1.8.7 SPECIFIED QUANTITIES | $71 |
Download this table: ·
Draw-down shape
Sources
LA Controller, Checkbook LA (pggv-e4fn), read live and grouped by po_num, which is populated on about 90% of payments. Council files link to the City Clerk's Council File Management System. The City's biggest contracts · The checkbook.